Mears Ltd v Costplan Services (South East) Ltd and others [2019] EWCA Civ 502

3 July 2019

Facts

The tenant (T) entered into an agreement for lease under which the landlord (L) agreed to procure the construction of two blocks of student accommodation. T agreed to take a long lease of the blocks following practical completion of the works.

The agreement prevented L from making any variations to the works which materially affected the size of the rooms. The agreement provided that a size reduction of more than 3% from the sizes shown on the original drawings was deemed material. 56 of the completed rooms were found to be more than 3% smaller than this tolerance level.

T sought a declaration that any failure to meet the 3% tolerance level was a material and substantial breach of the agreement for lease, allowing T to terminate the agreement or prevent the employer’s agent from certifying practical completion under the agreement.

Issue

Did T automatically have a right to terminate the agreement for lease or to prevent the employer’s agent from certifying practical completion under the agreement?

Decision

The deemed materiality reference in the agreement for lease determined whether there was a breach of contract in the first place, not whether that breach itself was material. As a material breach would allow the tenant to terminate the agreement (known as a repudiatory breach) or object to the issue of a practical completion certificate, it would not make commercial sense if any breach of the agreed size tolerance level (e.g. an undersized bin store) automatically had such an effect.

Points to note/consider

  1. T will be entitled to damages from L for breach of contract and will not necessarily be obliged to complete the long lease. Although the Court of Appeal ruled that not every breach of the room size tolerance provision was material, that did not mean that the breaches in this case were not material or repudiatory (that was a question of fact to be decided on another day).
  2.  The Court of Appeal did acknowledge that parties to a contract can agree that a breach of a particular clause will amount to a material breach (it was just that  L and T had not done so here). What this case does show therefore is that if a tenant does not want to have to complete its lease if a particular obligation in an agreement for lease is breached, it is important to provide expressly for this in the agreement.
  3. As is usually the case, the concept of practical completion was not defined in the agreement for lease. This case is therefore interesting for Coulson LJ’s comments on the meaning of practical completion. In particular:

  • practical completion is a state of affairs in which works have been completed, free from patent defects, other than trifling ones that can be ignored;
  • it is easier to recognise than define;
  • there is no difference with patent defects between an item of work which is outstanding and an item of defective work which requires to be remedied (snagging lists can cover both);
  • whether or not a defect is trifling is a matter of fact and degree and just because students could live in the property did not necessarily mean that the property was practically complete; and
  • the fact that a defect is irremediable (as in this case) does not of itself prevent practical completion.

focus on...

Legal updates

A pragmatic and common sense approach to Housing Disrepair during COVID-19?

The resolution of disrepair issues will not always be straightforward in the new world in which we find ourselves. The Ministry of Housing, Communities & Local Government has therefore released Guidance for Landlords and Tenants.

View

Legal updates

Cabinet Office advice for contractual behaviour which is impacted by the Covid-19 emergency

On the 7th May 2020, the Cabinet Office released its guidance on responsible contractual behaviour for both public and private sectors relating to the performance and enforcement of contracts which have been “materially impacted” by the coronavirus.

View

Legal updates

Welcome Land Registry change of practice on executing deeds

In view of the difficulties of arranging for deeds to be printed and distributed in the current climate the Land Registry announced on 1 May that certain deeds signed using the Mercury signing approach will be accepted by the Land Registry for registration purposes.

View

Legal updates

New measures announced to protect the High Street from aggressive rent collection and closure

In a move that will be greatly welcomed by retailers, the Government announced on 23 April that it will introduce new measures to safeguard the High Street against aggressive debt recovery actions during the coronavirus pandemic.

View

The content on this page is provided for the purposes of general interest and information. It contains only brief summaries of aspects of the subject matter and does not provide comprehensive statements of the law. It does not constitute legal advice and does not provide a substitute for it.

David Harris

David Harris

Professional Development Lawyer

View profile

mailing list sign up



Select which mailings you would like to receive from us.

Sign up