Skip to main content
Share via Share via Share via Copy link

Securing data centre power: Strategic steps to navigate the UK's new grid connection regime

27 November 2025
Darren Ashworth

Britain's electricity grid faces unprecedented demand. With approximately 750 gigawatts queued for connection across the energy sector, UK data centre developers confront a dual challenge. Securing grid access is difficult, yet many operational facilities fail to utilise their full allocated capacity once power has been secured.

Understanding capacity wastage

The industry has faced a hidden inefficiency of stranded power. When a facility secured 100 MW but operated at 80 MW, those unused 20 megawatts remain unavailable for reallocation. This phenomenon, largely driven by factors such as dormant servers, suboptimal infrastructure deployment, cooling constraints, and excessive contingency margins, means operators have funded unused capacity while prospective projects wait indefinitely.

Britain's infrastructure legacy

Largely designed six to eight decades ago, the UK's electricity network lacks standardised architecture. Each regional connection requires bespoke engineering solutions tailored to local infrastructure. To compound this, determining a data centre's precise electrical requirements, accounting for server loads and cooling systems, requires intricate calculations leading to large design lead in times. 

Power demands can be extreme. Hyperscale data centres can exceed 100 MW of load according to industry studies. Against this backdrop, NESO’s 2025 pause on new transmission connection applications has pushed developers to consider acquiring existing agreements or waiting for reallocated capacity freed up by ‘zombie project’ removals.

Regulatory transformation: The gate framework

Ofgem's April 2025 approval of TM04+ reforms fundamentally restructures grid access. The previous chronological queuing system has been replaced with a merit-based approach prioritising project preparedness and strategic value to the energy system.

Under the new framework, projects that achieve ‘Gate 2’ status receive firm connection agreements with confirmed dates, locations, and milestones. Projects that do not yet satisfy the required readiness criteria are placed into ‘Gate 1’, where they receive indicative, non-binding timelines and are treated as lower-priority candidates for future connection slots.

Since Ofgem's approval of TM04+ reforms, further demand-specific queue management measures were proposed in November 2025 to address the continued surge in connection applications, reinforcing the importance of demonstrating genuine project readiness.

Demonstrating project readiness

Gate 2 qualification demands evidence through either:

Property rights: Such as freehold ownership, leases of at least 20 years, or options spanning 3+ years, satisfying minimum site area thresholds.

Regulatory approval: Submitted and validated Development Consent Order applications.

While transmission-connected demand projects (encompassing data centres) benefit from automatic strategic alignment qualification, Ofgem recognises that data centre developers, who typically secure property interests later than renewable energy projects, face compressed timelines for meeting land ownership criteria.

Planning framework developments

In December 2024, the National Planning Policy Framework was amended to explicitly require local planning authorities to plan for data centres, recognising their importance to the modern economy. Meanwhile, data centres were formally designated as Critical National Infrastructure (CNI). Large-scale data centre developers may opt into the Nationally Significant Infrastructure Projects (NSIP) consenting regime under the Planning Act, meaning decisions are taken by the Secretary of State rather than local councils. 

While this route demands substantial upfront consenting work, it provides a potentially faster, more streamlined process for nationally strategic projects.

Critical deadlines

The Gate 2 evidence window for transmission projects opened in July 2025, prompting customers to submit proof of project maturity. Initial assessments by NESO and DNOs began in September 2025 for transmission-connected projects. Following detailed checks, final Gate 2 offers for transmission are expected by March 2026, and for distribution by May/June 2026 per published timelines.

Developers without secured land rights or planning consent risk being deprioritised as readiness requirements become more stringent.

Complementary requirements

Grid connection represents one component of a broader compliance framework including:

  • Operational fibre-optic connectivity ("lit" infrastructure).
  • Environmental Impact Assessments evaluating carbon footprint, water consumption, and acoustic impacts in line with planning requirements.
  • Biodiversity Net Gain obligations (in force from 2024) demonstrating measurable environmental enhancement.

Optimising facility performance

Advancing grid-connection engineering and facility design in parallel can compress development schedules, but precision remains critical. Implementing granular monitoring through power distribution units, circuit-level metering, and baseboard management controllers supports closer alignment between provisioned capacity and actual consumption. This reduces inefficiencies from the outset and strengthens long-term operational performance.

The evolving regulatory landscape directly influences development economics. Adjusted connection-queue processes and readiness criteria affect land-acquisition strategies, planning approaches, and financing arrangements. Earlier demonstration of deliverability can accelerate connection offers, thereby strengthening investment cases and shaping tenant negotiations.

Strategic positioning

The current reforms are targeted at speculative or non-progressing applications that occupy grid-connection capacity without demonstrable commitment. In response, data-centre developers must satisfy more stringent evidential requirements within compressed timeframes, particularly relating to documented land rights, planning status, and progress against engineering milestones.

Developers that secure land interests and planning approvals early, while designing facilities to maximise capacity utilisation, are better positioned to move through readiness gates and obtain revised connection dates. Where connection timing determines financial viability and inefficient capacity allocation restricts sector growth, proactive legal preparation combined with technically robust design distinguishes applicants capable of advancing to Gate 2 from those remaining in preliminary stages.

How we can help

We advise data centre developers on securing the land rights, planning consents, and regulatory positioning needed to demonstrate Gate 2 readiness while maximising every megawatt through facility design. To discuss your requirements further, please get in touch. 

Contact

Contact

Darren Ashworth

Partner

darren.ashworth@brownejacobson.com

+44 (0)330 045 1159

View profile
Can we help you? Contact Darren