it's about time: the court gives guidance on time bars in construction contracts

20 June 2019

This article is taken from June's public matters newsletter. Click here to view more articles from this issue.


Many of our public sector clients regularly undertake building works using NEC3 and NEC contracts and works worth an estimated £4 billion have been carried out, for example, under the Procure 21+ Framework, which is based upon the NEC3 ECC contract. Many clients will therefore want to keep abreast of developments in case law relating to these contracts.

The recent case of Sitol UK Ltd v Finegold and another [2018] acted as a harsh reminder of the importance of complying with contractual time limits. Sitol were engaged by the Finegolds to undertake tiling work as part of a large refurbishment project at their home under an NEC3 Engineering and Construction Short Contract. Importantly, as it was a residential project, the Construction Act was not applicable (as if the work was covered by the Act adjudication could be brought at any time).

Sitol brought proceedings against the Finegolds to seek enforcement of an adjudication decision that the Finegolds were liable to pay Sitol £44,838.38 for work done. The Finegolds argue that they should not have been named in the adjudication and enforcement proceedings, on the basis that Sitol had in fact contracted with Proman Ltd, who acted as their main contractor on their multi-million pound redevelopment project.

Crucially however, the Finegolds also argued that the referral to adjudication was made out of time. The contract in question required a party to refer any dispute to an adjudicator ‘within four weeks of becoming aware of it’, and it was clear that Sitol had not complied with this time bar.

The decision

In the enforcement proceedings it was held that the tiling contract was between the Finegolds and Sitol, and that Proman Ltd as their Project Manager had merely acted as agent.

It was further held that the dispute was referred to adjudication out of time. The dispute was brought to the attention of Sitol by letters from the Finegolds expressly rejecting their claim sent on 19 February 2018. Sitol then failed to issue a Notice of Adjudication or otherwise notify the Finegolds of the dispute until 25 April 2018, being outside the four week time limit.

As a result, summary judgment was declined by the Technology and Construction Court.

Implications

This appears to be the first case to apply the time limits set out in an NEC3 and NEC4 Contracts. There are a number of time limits in the NEC3 and NEC4 Contracts, and while it is important to remember that this particular case will not be applicable where the Construction Act applies, the decision is a clear indication that time limits will be enforced in all areas and not just adjudication.

The judge added that he had ‘no great enthusiasm’ for the point, but was bound to apply the law. It will be interesting to see whether attempts will be made in the future to dilute the impact of the provision and this decision.

Impact on the public sector

Public sector bodies should stay alert to all the ticking clocks within NEC3 and NEC4 contracts, as even if this particular decision on adjudication is limited to contracts outside the Housing Grants Act, missing any time bar will have serious consequences.

If you are unsure of how this applies to your contract, please contact us for further advice.

Receive our latest government sector news

Choose the way you want to keep up to date with our latest updates and insights. Sign up to our monthly newsletter or join the conversation with our team on LinkedIn.

Sign up to receive updates >

Follow our LinkedIn showcase page >

<>

training and events

17Sep

In-house lawyers' update Manchester office

Our next in-house lawyers' sessions will give in-house lawyers the tools and strategies for dealing with some of the problems caused by recent changes to the law.

View event

25Sep

In-house lawyers' update Nottingham office

Our next in-house lawyers' sessions will give in-house lawyers the tools and strategies for dealing with some of the problems caused by recent changes to the law.

View event

focus on...

Legal updates

Public matters - August 2019

This month includes third country bidders and goods in the EU procurement market, framework agreements, conservation newsletter, first ICO fines under GDPR and the government's MSA review response.

View

Legal updates

Third country bidders and goods in the EU procurement market

On 24 July 2019 the European Commission issued ‘Guidance on the participation of third country bidders and good in the EU procurement market’ which provides practical advice to EU contracting authorities on how to deal with bidders from outside of the EU.

View

Legal updates

Frameworks - still fit for purpose?

Frameworks feel like an institutional part of public procurement in the UK and in Europe. Last year Browne Jacobson undertook some market research with the CBI to look at public procurement from the private sector perspective.

View

Legal updates

Conservation newsletter - August 2019

Welcome to Browne Jacobson’s August 2019 conservation newsletter, looking at climate change, bird netting, Oak Processionary Moth, recent case law and legislation updates.

View

The content on this page is provided for the purposes of general interest and information. It contains only brief summaries of aspects of the subject matter and does not provide comprehensive statements of the law. It does not constitute legal advice and does not provide a substitute for it.

mailing list sign up



Select which mailings you would like to receive from us.

Sign up