does a breach of an obligation in an agreement for lease allow the tenant to refuse to complete the lease?

4 April 2019

A tenant who does not want to be forced to complete a lease if an obligation in the agreement for lease is breached must provide expressly for this in the agreement.

In a recent case, the agreement for lease prevented the landlord from making variations to the landlord’s works (the construction of student accommodation) which materially affected the size of the rooms. The agreement provided that a size reduction of more than 3% from the original drawings was deemed material. In contravention of this provision, the landlord built some rooms which were more than 3% smaller.

The Court of Appeal decided that although the parties could spell out exactly what type of breach would allow the tenant to terminate an agreement, that was not what the parties had done here and it would not make commercial sense if any breach of the agreed size tolerance level (e.g. an undersized bin store) automatically allowed the tenant to terminate the agreement.

In this case, the tenant is possibly facing the unpalatable prospect of having to complete a long lease of student accommodation with 56 rooms smaller than specified.

It makes sense to agree at heads of terms stage what breaches will give rise to termination so that both parties are clear from the outset and this can then be built into the agreement for lease.

related opinions

COVID-19 child protection practice - four months in - lessons learned so far

In June 2020 the University of Birmingham published a research briefing exploring the impact of the COVID-19 pandemic on child protection practice.

View blog

“Caution” is now the watchword when it comes to directly awarding public sectors contracts

The judicial review proceedings brought by the Good Law Project against the Department of Health and Social Care in relation to the £108m contract the Department awarded for PPE in April are about to shine a light on Regulation 32(2)(c) of the Public Contracts Regulations 2015.

View blog

Can an application to postpone a hearing be refused?

This case highlights the importance of Claimants obtaining their own medical evidence in such matters especially when it is pivotal to their claim.

View blog

A landlord’s promise, a tenant’s power

When it comes to leases, most people believe that landlords hold most of the power. However, in relation to long residential leases, the tables may well have recently turned in one respect at least following a recent Supreme Court decision.

View blog

David Harris

David Harris

Professional Development Lawyer

View profile

mailing list sign up



Select which mailings you would like to receive from us.

Sign up