Failing to assign the copyright in plans on or before completion could have meant that a seller’s notice to complete was invalid.

Facts

The sellers (S) entered into a contract to sell property for residential development to the buyer (B) for £2.225m. The contract obliged S to assign to B the copyright in plans and reports prepared by S’s architects (the Plans).

After a revised contractual completion date had passed without completion taking place, S served a notice to complete on B. As B then failed to complete within 10 working days from service of the notice to complete, S purported to rescind the contract (and forfeit B’s deposit).

B argued that S had not been ready, able and willing to complete when it served the notice to complete as S had not by then complied with its obligation to assign the copyright in the Plans to B.

Issue

Was S ready, able and willing to complete when it served its notice to complete (if not, the notice to complete would be invalid)?

Decision

The court agreed with B that a failure to assign the copyright in the Plans to B was a matter of substance (not an administrative formality) so potentially S could not be said to have been ready, able and willing to complete when it served the notice to complete.

Rather than assign the copyright, S had obtained from the architects a non-exclusive licence to reproduce the Plans. However, despite numerous opportunities to do so, B had never objected to this. By its conduct, B was taken therefore to have waived its right to insist on a full assignment of the copyright. Having therefore procured sufficient licences to use the Plans, S had accordingly been ready, able and willing to complete when it served the notice to complete.

Points to note/consider

1. Despite the outcome here, this case is an important reminder of what ready, able and willing to complete means when looking to serve a notice to complete. It usually boils down to whether there are matters of substance still outstanding or whether what is outstanding are merely administrative arrangements necessary to enable completion to take place within the time-frame specified in the notice to complete.

2. B argued that any waiver of its right to insist on an assignment of the copyright in the Plans was a material variation of the contract and therefore void for failing to comply with the formalities in section 2 of the Law of Property (Miscellaneous Provisions) Act 1989 (which applies to variations in a contract to dispose of an interest in land as much as it applies to the creation of such contracts). The court however decided that section 2 did not apply to a waiver of a right under a contract (as opposed to an express material variation).

training and events

26Jun

Managing procurement risks and challenges Exeter office, 1st Floor, The Mount, 72 Paris Street, Exeter, EX1 2JY

Have you ever received a letter challenging a regulated procurement procedure? Has your authority ever had proceedings issued against it for breach of the Public Contracts Regulations 2015? This all day workshop is designed to give you the confidence to understand the pressure points in procurement processes and how they can give rise to risk.

View event

focus on...

Legal updates

Public matters - May 2019

This month includes freedom of information, housing regeneration, Alexander Kuznetsov and London Borough of Camden, EU regulation standard form public procurement notices, expert evidence, child care and immigration, conflicts of interest, information law update, and environmental law.

View

Legal updates

The risks of 'accidentally' exchanging contracts

The recent case of Alexander Kuznetsov and London Borough of Camden serves as a reminder of the fundamental elements of a property sale contract and the risks of unintentionally exchanging contracts.

View

Redress schemes for abuse and misconduct - hear from our experts

The IICSA has a number of investigative streams, and one of its areas of focus is Accountability and Reparations.

View

Legal updates

Expert evidence

The law in relation to expert evidence is not straightforward and this article is intended as a walk through the major issues that may arise.

View

The content on this page is provided for the purposes of general interest and information. It contains only brief summaries of aspects of the subject matter and does not provide comprehensive statements of the law. It does not constitute legal advice and does not provide a substitute for it.

David Harris

David Harris

Professional Development Lawyer

View profile

mailing list sign up



Select which mailings you would like to receive from us.

Sign up