Court of Appeal reaffirms type of disputes entitled to be referred to adjudication under Construction Contracts Act 2013
On 13 November 2026, the Court of the Appeal in Ireland handed down its decision in Connaughton v Timber Frame Projects Ltd t/a Timber Frame Ireland [2026] IECA 216, upholding the High Court’s refusal to enforce an adjudicator’s award on the grounds that the Plaintiff’s claim for losses did not constitute a ‘payment dispute’ within the meaning of the Construction Contracts Act 2013 (the 2013 Act).
Background
This dispute arose from a 2023 construction contract between Albert Connaughton and Timber Frame Ireland (TFI), under which TFI agreed to construct a prefabricated timber-frame house for an agreed price of €138,867. The agreed payment schedule was front-loaded, reflecting the fact that the structure was prefabricated, and saw Mr Connaughton make payments totalling €124,891 between October 2023 and January 2024.
Work to erect the structure on site was due to begin in January 2024. TFI delivered some components later that year but carried out only a “miniscule amount” of assembly work on a date in May 2024. The components were left exposed to the elements and their condition deteriorated, rendering them unusable.
In the circumstances, Mr Connaughton treated the contract as having been terminated for repudiatory breach and sought repayment of the sums paid to TFI together with compensation for other consequential losses, such as the cost of completing the works. In October 2024, Mr Connaughton referred the dispute for adjudication under the 2013 Act. TFI did not participate in the adjudication and would therefore have been bound by the adjudicator's findings had he determined that a payment dispute existed.
The adjudicator assessed the claim, concluding that TFI’s failure to perform the contract within a reasonable time constituted a repudiatory breach of the contract and that the contract was terminated. The adjudicator awarded Mr Connaughton €184,119.87, comprising repayment of the €124,891 already paid to TFI by Mr Connaughton and compensation for consequential losses due to non-performance of the contract by TFI.
High Court decision
Mr Connaughton applied to the High Court for leave to enforce the adjudicator’s decision under section 6(11) of the 2013 Act. The High Court refused the application, finding that the claim did not constitute a ‘payment dispute’ within the meaning of the Act and that the adjudicator therefore lacked jurisdiction to determine the dispute. This decision was appealed by Mr Connaughton to the Court of Appeal.
Court of Appeal
The central issue before the Court of Appeal was whether Mr Connaughton’s claims constituted a ‘payment dispute’ capable of being determined by adjudication under section 6 of the 2013 Act.
The Court held that the scope of section 6(1) of the 2013 Act is limited to disputes as to whether one party is entitled to recover payment from the other in satisfaction of an obligation arising from the terms, express or implied, of the contract. This was not the case for Mr Connaughton, whose claim was fundamentally a claim for unliquidated damages for breach of contract.
The Court confirmed that payments under the 2013 Act, mean payments that discharge contractual obligations to make payments, and the mere fact that a claim for unliquidated damages for breach of a construction contract includes or comprises a claim for reimbursement of payments made under that contract cannot turn any part of that claim into "a dispute relating to payment arising under the construction contract”.
The Court emphasised that the purpose of section 6 of the 2013 Act is to ensure payment disputes under construction contracts are resolved speedily, through a provisional remedy that may be superseded by arbitration or court proceedings. In other words, ‘pay now, argue later’. The adjudication procedure is not a general mechanism to adjudicate on and award compensation for breaches of construction contracts. It is ill-suited to and does not provide a realistic timeframe within which to resolve claims of that nature.
Accordingly, the Court dismissed Mr Connaughton’s appeal.
The decision confirms that statutory adjudication under the 2013 Act is confined to resolving ‘payment disputes’. This contrasts with the regime in the UK, under which any dispute arising under a qualifying construction contract may be referred to adjudication, not just payment disputes.
For parties entering into construction contracts in Ireland, the practical message is to ensure that the contract includes clear provisions governing payments on termination and repayment obligations. Doing so can provide greater certainty for both parties, and may help establish a contractual payment entitlement capable of enforcement through adjudication under the 2013 Act.
For parties contemplating commencing adjudication proceedings under an existing construction contact, the framing of any such proceedings and / or relief sought, is crucial to preserve a party’s entitlement to rely on this form of dispute resolution and the enforceability of any award made on foot of same.
For more details on this topic, and if you are considering whether adjudication is a suitable avenue for resolving your dispute, please contact Darragh Killeen and Laura Finn.