MEAT methodology examined in recent case: Proximus v Council [2019]

12 February 2019

This article is taken from February's public matters newsletter. Click here to view more articles from this issue.


The General Court (the court) has dismissed an annulment application brought by Proximus SA/NV (Proximus) in a case which has reaffirmed existing case law that the ‘most economically advantageous requirement’ does not necessarily relate solely to prices.

Background

The Council of the European Union (council) invited tenderers to participate in a negotiated procurement procedure for the award of a framework contract for cybersecurity services. The services to be provided were separated under ‘service packages’.

According to the tender specifications, the contract was to be awarded to the tenderer who submitted the tender offering the best value for money. Specifically, the specification stated that the technical evaluation counted for 60% and the price offered countered for 40%.

In respect of the financial evaluation, a financial score was calculated for each service package by comparing the price calculated for one sub-criterion in a given tender with the sum of all tenders received for that sub-criterion, using a mathematical formula.

A weighting percentage was then applied to each service package and each tenderer given a financial score which corresponded to the weighted total of the scores assigned for each financial criterion.

Proximus was unsuccessful in its bid. In a letter to the council, it stated that the application of the price criterion appeared to be incorrect, in so far as it had obtained a lower score than that of the successful tenderer, although the latter’s tender had a higher total price. The council decided not to sign the contract with the successful tenderer whilst it reconsidered the contested decision.

The council eventually responded to Proximus’ letter, stating that it saw no reason either to reconsider its award decision or not to conclude the contract. The contract was signed with the successful tenderer in February 2017.

The proceedings

Proximus sought to challenge the award on the following grounds:

1. Infringement of Article 110(4) and Article 310 TFEU

Proximus argued that the formula set out in the tender specifications did not serve to select the most economically advantageous tender (and therefore was in breach of Article 110(4) TFEU), on the grounds that it reflected the relative price difference at the level of each service package, but failed to take into account differences in the total prices tendered. It also claimed that the formula discourages optimal financial tenders.

The court rejected all points of this argument, stating that the criteria adopted by a contracting authority to identify the most economically advantageous tender need not necessarily be quantitative or related solely to prices. It said that it is sufficient that such criteria can be applied objectively and uniformly in order to compare the tenders, and that they be clearly relevant for identifying the most economically advantageous tender. Proximus failed to show that the council’s formula was not capable of identifying the most economically advantageous tender.

Proximus also argued that the weighting system applied was arbitrary and that the council had breached Article 310 TFEU by not abiding to the principle of sound financial management. It was unsuccessful in both of these arguments.

2. Infringement of the general principles of transparency, non-discrimination and equal treatment

Proximus claimed that an evaluation method that does not give the best score to the tenderer offering the lowest price or cost infringes the general principles of transparency, non-discrimination and equal treatment.

The court disagreed, stating that it was apparent from the information put before it that the evaluation method and weightings of the service packages were clearly set out in the tender specifications.

Moreover, the information submitted did not indicate that the tenderers were not given the same information and treatment when the tenders were evaluated.

What does this mean for you?

In this case, the council had applied the correct methodology and was able to provide supporting evidence as proof. As such, it is essential that a contracting authority is comfortable that it has designed its evaluation method in a way that such criteria can be applied objectively and uniformly in order to compare the tenders, and that they be clearly relevant for identifying the most economically advantageous tender.

If you need help designing an evaluation methodology that is appropriate for your procurement of goods/services, please do get in touch.

Receive our latest government sector news

Choose the way you want to keep up to date with our latest updates and insights. Sign up to our monthly newsletter or join the conversation with our team on LinkedIn.

Sign up to receive updates >

Follow our LinkedIn showcase page >

<>

training and events

26Jun

Managing procurement risks and challenges Exeter office, 1st Floor, The Mount, 72 Paris Street, Exeter, EX1 2JY

Have you ever received a letter challenging a regulated procurement procedure? Has your authority ever had proceedings issued against it for breach of the Public Contracts Regulations 2015? This all day workshop is designed to give you the confidence to understand the pressure points in procurement processes and how they can give rise to risk.

View event

focus on...

Legal updates

Public matters - May 2019

This month includes freedom of information, housing regeneration, Alexander Kuznetsov and London Borough of Camden, EU regulation standard form public procurement notices, expert evidence, child care and immigration, conflicts of interest, information law update, and environmental law.

View

Legal updates

The risks of 'accidentally' exchanging contracts

The recent case of Alexander Kuznetsov and London Borough of Camden serves as a reminder of the fundamental elements of a property sale contract and the risks of unintentionally exchanging contracts.

View

Redress schemes for abuse and misconduct - hear from our experts

The IICSA has a number of investigative streams, and one of its areas of focus is Accountability and Reparations.

View

Legal updates

New EU regulation to establish standard form public procurement notices

The digital transformation of public procurement has been a hot topic and the European Commission recognises that standard form notices are instrumental in that transformation.

View

The content on this page is provided for the purposes of general interest and information. It contains only brief summaries of aspects of the subject matter and does not provide comprehensive statements of the law. It does not constitute legal advice and does not provide a substitute for it.

mailing list sign up



Select which mailings you would like to receive from us.

Sign up