Re Q & M [2026] EWFC 292: Practical lessons for local authorities on care proceedings delay

24 November 2026
Naomi De Silva

Ms Justice Henke has used a recent judgment to call for systemic change after care proceedings involving two siblings ran for almost two years, nearly four times the statutory 26-week limit. The case, Re Q & M, is not unusual. It is the latest in a line of judgments that identify the same pattern of preventable failure: poor disclosure management, under-prepared witnesses, and court bundles nobody could navigate. 

The good news for local authorities is that most of these failures are fixable, and fixing them is squarely within local control.

What happened in Re Q & M?

The County Council brought care proceedings in respect of two siblings. By the time the case concluded, the youngest child was nearly three years old, meaning she had spent roughly two-thirds of her life as the subject of court proceedings. There had been 12 case management hearings. Several social workers had been involved across the life of the case. A social worker entered the witness box without adequate preparation and needed time to get ready. The court bundle ran to thousands of pages.

Ms Justice Henke was direct in her conclusion: change is necessary, and she expressed hope that the local authority would use the case as the basis for learning and improved practice.

What is striking is that none of these problems are described as arising from the case being unusually complex. They are described as process failures, the kind that cause adjournments, trigger further directions, generate more hearings, and (ultimately) leave children in interim arrangements for far longer than they should be.

The law is clear and it means what it says

Section 32 of the Children Act 1989 requires the court to timetable proceedings with a view to disposal "without delay" and, crucially, "in any event within twenty-six weeks" from issue. Extensions are available only where necessary to resolve proceedings justly, they are not a backstop for cases that simply drift.

Practice Direction 12A (the Public Law Outline) is the operational framework designed to hold the timetable together. It sets out precisely what must be ready at issue: chronology, social work statement, genogram, assessments relied on, care plan, and how the court should manage the case through each stage.

When a judge uses the phrase "unconscionable delay", the question being asked implicitly is: what controllable steps were not taken that allowed the case to slip past 26 weeks and keep going?

That is the question local authorities and their lawyers should be asking themselves, before issue, not after.

This is a system-wide problem, not an isolated bad case

It is tempting to treat a case like Re Q & M as an exceptional case, an unusually complex matter with an unusual combination of problems. The national data does not support that reading.

The pressure points Ms Justice Henke identified, professional churn, unfocused bundles, late disclosure, are consistent with what the NAO and Ministry of Justice statistics show are system-wide contributors to delay, not exceptional features of difficult cases:

  • The national average duration for care and supervision proceedings has been running at around 40 weeks against the 26-week statutory limit, meaning the average case is already more than a third over the legal timeframe before it concludes.
  • More than 4,000 children were in cases that had not resolved after 100 weeks, for many of those children, proceedings will have been a feature of their entire conscious lives.
  • The NAO found that family justice services cost public bodies over £1.8bn in 2023-24, and identified weak accountability across government departments as making it difficult to understand what is driving the problem, or whether any intervention is working.
  • The NAO specifically identified increased evidence requirements, higher case complexity, professional capacity pressures, and administrative inefficiency as systemic contributors to delay, not one-off case features.

What the statistics also show is that courts are increasingly scrutinising pre-proceedings conduct in delayed cases. The question being asked is not just "why did this take so long?" but "what was the state of the evidence and the care planning when you issued?"

The bundle problem: More paper is not more protection

One of the most practical, immediately fixable issues in Re Q & M was bundle quality. The court was faced with thousands of pages of material with no clear focus. Practice Direction 27A is explicit: unless the court directs otherwise, an electronic bundle is capped at 350 A4 pages, and going beyond that requires the court's permission on the basis that it is necessary to dispose of the case justly.

Over-large bundles are not a sign of thorough preparation. They can be a sign that insufficient focus has been placed on what the Court really needs to know, or of poor editorial judgment, and they create real risk. They slow hearings, increase preparation time for all parties, and, as this case illustrates, make it harder for social work witnesses to focus on what actually matters. A witness navigating thousands of pages of material is a witness who is more likely to struggle in the box.

Indeed, a good bundle should be seen as an opportunity to put key issues and facts before the Judge in as clear and as comprehensible a way as possible. Making it easy for a Judge to understand the decision they have to make and the material relevant to it is genuine opportunity to secure that decision with speed and efficiency. 

If your authority's bundle process does not reliably enforce PD27A discipline, the likely consequence is delay, and, increasingly, judicial comment.

Practical takeaways from Re Q & M judgment

Introduce a one-page 'Delay Risk Register' for every case

The most effective change local authorities can make is to make delay risk visible, and to do so early, before it becomes a problem. A short, jointly owned register (team manager and LA lawyer) that is reviewed at each key stage is not bureaucracy. It is a way of demonstrating that the authority actively managed the statutory timetable rather than simply experiencing what happened to it.

Suggested fields:

  • Continuity risk: Is the allocated SW stable? Is there a handover plan if not?
  • Disclosure readiness: Are core records complete pre-issue? Are there known gaps in third-party disclosure?
  • Care plan linearity: Is there a clear permanence pathway with a realistic timetable?
  • Family and friends assessment risk: Are viability assessments scoped, timetabled, and decision points clear?
  • Bundle risk: Estimated page count; what is being excluded and why?
  • Witness risk: Is the allocated SW prepared and stable as the identified witness at final hearing?

Think 'court-readiness', not just 'court-activity'

A surprising amount of delay comes from issuing too early, not because the facts do not justify issue, but because the documentation is not coherent enough to drive the case forward cleanly. Documents exist, but assessments do not answer the right questions. The care plan exists, but it is not linear. Disclosure exists, but it is not indexed.

At issue, the following should be in place:

  • The chronology and social work statement are internally consistent and match the threshold document.
  • The care plan is outcome-driven: what order is sought, why, and what is the permanence route?
  • The disclosure pack is complete and indexed - so that 'missing records' are discovered before issue, not during it.

By the case management hearing (days 12–18):

  • It should be possible to state precisely what evidence is needed, and what is not.
  • Any application to extend the timetable should be evidence-based, not a default position.

Fix any handover problem before it creates a crisis

Where cases run beyond 26 weeks, professional changes become more likely, not less. The consequences of an unmanaged handover compound delay: a new social worker needs time to get across the case, directions may need revisiting, and witness continuity is disrupted.

Even where changes are unavoidable, the impact can be substantially reduced by:

  • A pre-agreed handover pack covering key issues, chronology updates, a disclosure log, and the objectives for the next hearing.
  • Early identification of who will give evidence at final hearing, and protecting that person's involvement in the case.
  • Timetabled witness preparation sessions, not a rushed conversation on the morning of the hearing.

The 'ill-prepared witness → adjournment → further delay' pattern identified in Re Q & M is one of the most common and most avoidable contributors to prolonged proceedings.

Conclusion

Re Q & M is a useful judgment not because it tells local authorities anything radically new, but because it names, specifically and publicly, the operational failures that cause delay. In a system where the average case still takes around 40 weeks, and where courts are increasingly focused on pre-proceedings conduct, the local authorities best placed to protect children's timescales are those that treat delay risk as something to be managed from the outset, not explained after the event.

The tools to do that are not complicated. A focused care plan, disciplined disclosure, a properly curated bundle, and a prepared witness are the basics of good public law practice. They are also, as this judgment makes clear, the basics that courts will continue to insist upon.