When is a subsidy decision actually made?
The judgment of the Competition Appeals Tribunal (CAT) in Mr Graham Thomas and Others v Durham County Council provides much needed clarity on the question of when a subsidy ‘decision’ has been made and so the clock starts for challenges.
The question
Setting aside broader competition law matters, the key subsidy question for the Tribunal was whether it had jurisdiction to review a subsidy decision under section 70(1) of the SCA where only a provisional or "in principle" decision has been taken, and the public authority had yet to reach a conclusion.
The Tribunal’s analysis
The Tribunal's prior judgment in Weis v Greater Manchester Combined Authority was a key starting point. In that case, a decision in principle to grant loans had been taken on 22 March 2024, but due diligence was still ongoing and GMCA denied that a reviewable subsidy decision had been taken. Mr Weis nevertheless filed his subsidy appeal on 7 June 2024 seeking an expedited review.
The Tribunal in Weis held that although the borrowers did not have an enforceable right to financial assistance until the date of entry into the loan agreements, this did not mean that there was no challengeable subsidy decision before then. It was concluded that the subsidy decision within the meaning of section 70 was taken on the date of the in-principle decision.
In Thomas, it was confirmed that a reviewable decision under section 70(1) may precede the execution of formal legal documents such as a loan or grant agreement. However, the requirement under section 70(1) for the public authority to have taken a "decision to give a subsidy" cannot be met where that decision is only a provisional or an "in principle" decision that is subject to further consideration and review itself.
In reaching this conclusion the Tribunal focused on four key reasons:
- The SCA's statutory scheme requires that a public authority undertakes a subsidy control assessment before deciding to give a subsidy. It does not make sense to apply the SCA’s scheme to provisional decisions.
- Reviewing provisional decisions would be impractical as it would be difficult (if not impossible) for the Tribunal to effectively review a decision that had not yet been made.
- The pre-action information regime supports a "final decision" approach. Section 70(1) is not intended to be operative in the wake of a provisional decision.
- The time limits cannot operate against a provisional decision.
The outcome
The Tribunal took the clear view that the Council had not taken a final decision to grant two of the grants and so concluded that it did not have jurisdiction to review either of those proposed grants under section 70(1).
The Tribunal struck the claim out rather than staying it. There was no clear timeframe for a final decision on either grant, and any fresh subsidy claim would require comprehensive rewriting to reflect the final terms and the Council’s assessment under the subsidy control principles. The Tribunal advised that once final decisions have been made, the Claimant could file fresh applications for review pursuant to Section 71 and rule 98A.
Key takeaways
- Only a formal, final decision to give a subsidy triggers the CAT's jurisdiction under section 70(1) – not a provisional or conditional decision.
- That said, a reviewable decision can be taken before the beneficiary acquires an enforceable legal right to the money.
- Whether a decision is truly final will depend on whether what remains outstanding is:
(a) administrative formality; or
(b) ongoing (and substantive) deliberation.
- Public authorities need to be attentive to internal decision-making processes and note when the process moves from provisional to final. Once final, the windows for challenge and entry on the database open.
- Prospective challengers should not rush to court before a final decision is taken. If they do, they are risking an immediate strike-out. Conversely, challenges should still be brought promptly once that reviewable decision is made to avoid being timed out. We expect many subsidy cases will hinge on whether a reviewable decision has taken place given the short timescales for challenge and broad range of decision-making processes.
- Different points in the decision-making process may be deemed to be reviewable depending on whether a subsidy or no-subsidy approach is taken by the authority. This is because a no-subsidy decision may have fewer outstanding points to be addressed (such as a subsidy principle assessment of compliance), leading to that being a more ‘final’ decision. Again, we expect this to provide fertile ground for challenges.
Browne Jacobson has one of the largest dedicated subsidy control teams in the UK, led by Alex Kynoch. We advise all tiers of government and subsidy recipients on subsidies and clients value our pragmatic, solution-focused advice. For more information regarding subsidy control law, please contact our specialist team.
Contact
Alex Kynoch
Partner
alex.kynoch@brownejacobson.com
+44 (0)115 976 6511
Matthew Thompson
Solicitor Apprentice
matthew.thompson@brownejacobson.com
+44 (0)330 045 2487
Related expertise
You may be interested in...
When is a subsidy decision actually made?
Bristol Airport v Welsh Ministers: A landmark Subsidy Control Act ruling
Government investment in zero emission charging infrastructure: Legal comment
Subsidy control lessons from the New Lottery case
Expert evidence in subsidy control challenges: Tribunal draws a firm line
What lessons does Weis v GMCA have for public authorities delivering regeneration projects?
Innovative housing strategies for councils after ‘asylum hotels’ injunction
Public matters: August 2025
Changes to the subsidy control statutory guidance August 2025: What public authorities need to know
Greater Manchester Combined Authority v developer: Key lessons on subsidy control for local authorities
Subsidy control cases coming into land
Government publishes response to consultation on Subsidy Control Regime
Practical guide to the English Devolution Whitepaper
Refining the UK subsidy control regime consultation
The housing benefit subsidy deficit: Strategies for funding temporary accommodation
The legal and planning hurdles that must be overcome to get Great British Energy generating
Update on local authority owned companies: Part 1 subsidy control
Does the subsidy control regime already need changing for the government to kickstart economic growth?
The transparency regime under the Subsidy Control Act - how it could be improved
Subsidy control guidance update - welcome guidance on 'small subsidies' introduced
Subsidy control: Guide to streamlined routes for universities
Subsidy control - lessons learned in the first year
Review of a subsidy control decision: The Durham Company Ltd v Durham County Council, 27 July 2023
Browne Jacobson advising the Welsh Government on the delivery of significant number of renewable energy projects
Subsidy control lessons to be learnt from Bulb
Public matters - February 2023
Government introduces first Streamlined Subsidy Schemes under new regime
Public matters - January 2023
The Subsidy Control Act 2022. Putting the new regime into practice
Government provides guidance on new Subsidy Control Database and the calculation of their value
The impact of the new Subsidy Control regime on public regeneration projects
Subsidy Control Act 2022: economic queries
In July, the long-awaited statutory guidance on the Subsidy Control Act 2022 (Act) was published in draft form (Draft Guidance). A consultation on the draft guidance has recently ended and the results have not yet been published – it may therefore change before the final version is published.
Economic activity for the purposes of the Subsidy Control Act 2022
When carrying out a mix of activities it can be less clear if it is 'economic'. We look at the impact on local authorities & charities.
The UK’s first domestic subsidy control case
We waited more than a year for it, but the wait is over – we finally have a domestic case on the new subsidy control regime.
Subsidy control webinar - 30 March 2022
In this on-demand session, Alex Kynoch and Angelica Hymers explore the practicalities of complying with the new Subsidy Control Bill, and the impact of illustrative guidance and policy statements recently published by the Government.
The Subsidy Control Bill – Illustrative Guidance and Regulations – legal certainty vs flexibility
It has been a turbulent couple of years for those involved in subsidy control, and 2022 will be equally challenging. The Subsidy Control Bill (Bill) will take effect in 2022.
Subsidy control regime: new Bill working its way through Parliament
2022 is the year in which the UK’s new post-Brexit subsidy control regime will take effect. The new Subsidy Control Bill will form the backbone of the UK’s new subsidy control regime. The new Bill will replace the EU’s state aid rules, which applied until the end of the Brexit transition period.
New Year, New Subsidy Control Regime Part 2: Schemes, enforcement and transparency under the Subsidy Control Bill
In the first part of this article, we discussed the application of the Subsidy Control Principles. In part 2, we look at how Streamlined Subsidy Schemes will be used to grant certain subsidies more quickly, and at the enforcement and transparency provisions of the Bill.
New Year, New Subsidy Control Regime Part 1: The principles, restrictions and exemptions under the Subsidy Control Bill
The repeal of the State aid rules and their replacement by the regime stemming from the UK-EU Trade and Co-operation Agreement (TCA) in 2021 meant that practitioners and public bodies had to acclimatise to a new, more flexible but less certain approach.
Browne Jacobson’s government & infrastructure lawyers advise on first South West based green hydrogen production project
Browne Jacobson’s specialist government and infrastructure team have advised Canford Renewable Energy Ltd on the delivery of its Dorset Green H2 facility.