Contract termination in Covid-19 times

12 October 2021

The ‘new normal’ has brought with it a variety of different challenges and it has had an impact on nearly all facets of our lives. 

Many public (and indeed private sector) bodies have had to consider how the contracts they have entered into prior to the pandemic respond when performance of those contracts is delayed and frustrated as a result of Covid-19. Although each contract will need to be considered on its own merits, how a contract responds to Covid-19 will often hinge upon whether the definition of force majeure (if there is one) is wide enough to capture the present circumstances.

The  courts have offered some guidance in the recent case of Dwyer (UK Franchising) Ltd v Fredbar Ltd which applies previous guidance about the implied duty of rationality in Braganza v BP Shipping Ltd [2015] UKSC 17.

Facts of the case

Dwyer (UK Franchising) Ltd (‘Dwyer’) and Fredbar Limited (‘Fredbar’) entered into a franchising agreement (‘Agreement’) in October 2018. Dwyer is a Franchisor of Drain Doctor, which is a substantial plumbing and drain repair services franchise. Fredbar was a Drain Doctor franchisee in accordance with the terms of the Agreement, which gave Fredbar the exclusive right to trade within nine postcode areas in Cardiff for a period of 10 years.

The agreement included the following force majeure clause: “This Agreement will be suspended during any period that either of the parties is prevented or hindered from complying with their respective obligations under any part of this Agreement by any cause which the Franchisor designates as force majeure including strikes, disruption to the supply chain, political unrest, financial distress, terrorism, fuel shortages, war, civil disorder and natural disasters…”

Fredbar’s owner was advised by the NHS on 24 March 2020 that his son was vulnerable and he was advised to isolate at home for 12 weeks. Fredbar had also experienced a drop of service demand and due to these circumstances, requested a suspension of the contract under the force majeure clause. He cited both reasons for wanting to suspend the Agreement under the force majeure clause.

This was rejected by Dwyer, who focussed on the effect of the Covid-19 pandemic on Fredbar’s business rather than personal position. Dwyer also noted that Drain Doctor was a key worker service.

Dwyer offered to waive payment during the isolation period which was accepted by Fredbar. Fredbar then sought to terminate the franchise agreement on 16 July 2020 on various grounds, including Dwyer’s refusal to suspend the Agreement under the force majeure clause. Fredbar’s owner stated that even if Fredbar was not entitled to terminate the Agreement, Fredbar no longer was bound by its terms. Dwyer asserted that Fredbar’s actions amounted to repudiatory breach. Dwyer terminated the agreement on 19 August 2020 and brought a claim for damages.

The court considered whether Dwyer executed their discretion under the force majeure clause correctly. They applied the principles set out in Braganza v BP Shipping Ltd. The court found that there was an implied term for Dwyer to take into account all matters that are relevant, exercise their discretion honestly, in good faith and genuinely and that Dwyer was in breach of this duty. Following this, the court asserted that Dwyer should have taken into account that Fredbar was a small business, thus their services were significantly disrupted by the owner’s need to self-isolate. Dwyer failed to recognise this and because of that failure, Dwyer had acted irrationally and had not considered the relevant issues. Fredbar would have been entitled to terminate the Agreement. However, because Fredbar accepted Dwyer’s offer to waive payment, Fredbar had affirmed the Agreement.

The court therefore ruled that by seeking to terminate the contract, Fredbar had committed a repudiatory breach as Fredbar had no right to terminate the Agreement after accepting the offer. Following which Dwyer could then validly terminated the agreement.

Considerations going forward

If a party needs to exercise discretion in deciding if Covid-19 is a force majeure event, the party should ensure its consideration complies with Braganza. This means that parties should ensure that:

  • They are familiar with the relevant contractual provisions.
  • They asses and respond to each claim within the timescales and in line with the provisions set out in the contract.
  • They keep records of contemporaneous events and of all correspondence in connection with the claims.
  • When making the decision take care to:
    • consider all relevant material including business and if relevant, personal circumstances for smaller contractors; and
    • exercise discretion honestly, in good faith and genuinely.

Parties alleging a force majeure event should be careful when accepting a solution to the Covid-19 problems. They may be inadvertently accepting a repudiatory breach, which may prevent them from later terminating the contract for force majeure.

Focus on...

Legal updates

Recovering monies from an individual? Don’t forget about the Pre-Action Protocol for Debt Claims

The PAPDC does not apply to business to business debt only if the debtor is a sole trader. Much more information is required under the PAPDC within a letter of claim and debtors should be given more time to respond along with an opportunity to make payment proposals throughout the pre-action process.

View

Legal updates

Mandatory directing off-site

On 17 September 2021, the High Court handed down judgment in the case that covers some important points in relation to directing pupils off-site and is one of the few cases that covers the powers of schools to do so.

View

Legal updates

Public Matters - September 2021

Updates include the UK Hydrogen Strategy and IPA assistance with PFI contract expiry.

View

Legal updates

The UK Hydrogen Strategy: an overview

Outline of the Government’s ambitious Hydrogen Strategy and how we can support low carbon energy projects and related queries.

View

The content on this page is provided for the purposes of general interest and information. It contains only brief summaries of aspects of the subject matter and does not provide comprehensive statements of the law. It does not constitute legal advice and does not provide a substitute for it.

Mailing list sign up

Select which mailings you would like to receive from us.

Sign up