Joint Contracts Tribunal (JCT) and New Engineering Contract (NEC) - which drafting works best, and where are the traps for the unwary?
This article is taken from June's public matters newsletter. Click here to view more articles from this issue.
Early contractor involvement can help smooth the way for large or complex construction projects, but it is not without its pitfalls. If not drafted properly, an Authority may find itself shackled to a contractor it no longer wants to work with or facing inflated construction costs with no easy way out. Joint Contracts Tribunal (JCT) and New Engineering Contract (NEC) now provide off-the shelf options for early contractor involvement, but which drafting works best, and where are the traps for the unwary?
Early contractor involvement, or two-stage tendering, splits the tendering process into two stages. During stage one the designs, cost estimates and other pre-construction elements are finalised in anticipation of the contractor being engaged to carry out the works under a building contract which forms stage two.
While this approach does imply additional costs at the early stages of a project, for large or complex projects the extra costs at design stage may be justified if, as a result, costly hold ups during construction are avoided.
When using JCT contracts, the first stage of the tendering process often results in these works being undertaken using a Pre-Construction Services Agreement (PCSA). When using NEC contracts, the first stage is often undertaken using NEC Early Contractor Involvement (ECI) clauses.
The JCT first published two forms of pre-construction services agreement in 2008 and these closely follow the terms and approach used in other JCT contracts. They are designed to be used with other JCT contracts, including the JCT Standard Building Contract and JCT Design and Build Contract.
Employers and contractors already familiar with JCT construction contracts are likely to feel at home with the JCT PCSA, while those that struggle with the traditional contract terminology and detailed approach used in JCT contracts may not.
As with existing JCT contracts, risk allocation is largely fixed, there is no proactive early-warning procedure, and the contractor claims for more time and money after a risk event occurs. An issue specific to the PCSA is that, unamended, the Contractor has no responsibility for design unless and until the main building contract is entered into.
The implication is that the contract must be modified to transfer risk, and clarify which party is responsible at which stage for any defects that may arise. This may include amendments to the execution clauses if the employer wishes to execute the PCSA as a deed and increase the limitation period for claims against the contractor to 12 years. As drafted, the JCT PCSA is designed to be executed as a contract under hand, with a limitation period of 6 years.
In the event of a dispute, the use of the established JCT approach is likely to mean the courts will be able to draw on existing case law on JCT contracts and terminology.
The NEC "early contractor involvement" clauses for use with the ECC, Options C and E, have now been incorporated as ECC Option X22. The ECI clauses are designed to merge seamlessly with the NEC4 ECC contract, and so do not require the negotiation of an additional separate PCSA.
In contrast with the JCT approach, NEC contracts include only limited details, leaving the parties to supplement these with negotiated Z clauses. The same language that is used across the NEC contract suite is used in the ECI clauses. The Cabinet Office has recommended that all public sector construction contracts should be upon NEC forms of contract.
The ECI clauses address issues likely to arise during a two-stage tendering process, for example, recognising that the Authority is likely to have relied on proposed key people in the contractor’s team in deciding which tender to accept and requiring the contractor to maintain these named key people in post.
To incentivise cost saving by the contractor the ECI clauses allow for the contractor to be paid a share of any saving on the budget, but the burden for cost overruns is placed on the Authority. Whilst this may work for an Authority which is experienced in operating construction contracts, for one-off contracts or Authorities that lack this experience the ECI approach may not be appropriate, particularly given the costs involved in halting and restarting the design process with a new contractor.
There are clear differences between the JCT and NEC approaches to two-stage tendering pre-construction. In choosing between them, factors to consider will include policy considerations, the likely approach to construction of the works under the subsequent building contract, and perhaps most importantly the experience of the team that will be administering the contract.
If the team ordinarily uses NEC contracts, then that may be the sensible option and vice versa if they are used to using JCT contracts.
If the team administering the contracts has little experience in administering either NEC or JCT forms of contract, it is usually considered that a JCT is the easier to administrate as it requires less ongoing management than an NEC contract.
If you need further information on early contractor involvement, please do get in touch and we would be delighted to assist.
Law firm Browne Jacobson has collaborated with Wiltshire Council and Christ Church Business School on the launch event of The Council Company Best Practice and Innovation Network, a platform which brings together academic experts and senior local authority leaders, allowing them to share best practice in relation to council companies.
In the Autumn Statement delivered on 17 November, rises to the National Living Wage and National Minimum Wage rates were announced, to take effect from 1 April 2023.
Announced in September but scrapped on 17 November the investment zone proposals were very short lived. The proposal has now morphed into the proposal for a smaller number of clustered zones earmarked for investment.
Settlement agreements are commonplace in an employment context and are ordinarily used to provide the parties to the agreement with certainty following the conclusion of an employment relationship.
On 2 November 2022, the Supreme Court handed down its judgment in the much awaiting case of Hillside Parks Ltd v Snowdonia National Park Authority [2022] UKSC 30. The Court’s judgment suggests that the long established practice of using drop-in applications is in fact much more restricted than previously thought. This judgment therefore has significant implications for both the developers and local planning authorities.
In ‘failure to remove’ claims, the claimant alleges abuse in the family home and asserts that the local authority should have known about the abuse and/or that they should have removed the claimant from the family home and into care earlier.
Logistics company Eddie Stobart has been fined £133,000, after a series of failures which took place whilst excavation work was carried out, exposing its staff to asbestos.
Browne Jacobson has appointed Amy Chapman, the former Group Legal Director of global built environment experts Mace Group, as its first Non-Executive Director (NED) of its Construction & Real Estate sector strategy board.
Across the UK, homelessness is an urgent crisis, and one that is set to grow amid the rising cost of living. Local authorities are at the forefront of responding to this crisis, but with a lack of properties that are suitable for social housing across the UK, vulnerable individuals and families are often housed in temporary accommodation.
Updates include UK Shared Prosperity Fund, contracts, Subsidy Control Bill, data controller liability, Government Covid-19 procurement and Highway Code revisions.
The complex and rather nebulous transitional subsidy control regime set out in the UK-EU Trade and Co-operation Agreement and the UK’s wider international commitments has made it difficult for public authorities and those working with them to proceed with certainty where subsidies are involved.
Investment zones have been introduced by the Conservative party to get the United Kingdom (UK) ‘working, building and growing’. They are to be designated sites which provide time-limited tax incentives, streamlined planning rules and wider support for local growth to encourage investment and accelerate the development of housing and infrastructure that the UK needs to drive economic growth. Processes and requirements that slow down development will be stripped back with the intention of attracting new investment.
Created at the end of the Brexit transition period, Retained EU Law is a category of domestic law that consists of EU-derived legislation retained in our domestic legal framework by the European Union (Withdrawal) Act 2018. This was never intended to be a permanent arrangement as parliament promised to deal with retained EU law through the Retained EU Law (Revocation and Reform) Bill (the “Bill”).
It is clear that the digital landscape, often termed cyberspace, is a man-made environment, in which human behaviour dominates and where technology both influences and aids our role in it — through the internet, telecoms and networked computer systems, which are often interdependent. The extent to which any organisation is potentially vulnerable to cyber-attack depends on how well these elements are aligned.
Three months on from the commencement of the new statutory Integrated Care Systems (ICS) Anja Beriro and Gerrard Hanratty reflect on the main themes and issues that have come from the new relationship between local government and health.