The Planning and Development Act 2024: The provisions that matter
Ireland's planning system underwent its biggest legislative overhaul in almost 25 years when the Planning and Development Act 2024 (the '2024 Act') was passed into law. On 26 November 2026, the Planning and Development Regulations 2026 come into operation alongside the commencement of the remaining provisions of the 2024 Act. The commencing provisions include Part 4 of the Act, which governs how planning permissions are granted and how conditions attached to those permissions are discharged.
The commencement is being discussed at Cabinet this week, with Minister for Housing James Browne and Minister of State for Planning John Cummins bringing a memo to Government ahead of Thursday. Speaking to the reforms, Minister Cummins has stated: "Planning cannot remain a system where delay is accepted as inevitable and costs spiral. I am determined to end that culture and introduce a system that facilitates development, not frustrate it."
For developers and contractors, here are the key points to note.
The critical cut-off: Midnight on 25 November 2026
Irish planning authorities are operating a strict statutory cut-off between the legacy regime and the new framework:
- Applications lodged before midnight on Wednesday 25 November 2026: Any valid planning application received by a local planning authority or An Coimisiún Pleanála before midnight on 25 November will continue to be assessed, decided, and appealed under the Planning and Development Act 2000 (the '2000 Act').
- Applications lodged on or after Thursday 26 November 2026: Any new planning application submitted from Thursday onwards is governed exclusively by the 2024 Act and the new 2026 Regulations.
Immediate risk of automatic invalidation
Local authorities across Ireland have issued strong warnings regarding transitional documentation. Any planning application lodged on or after 26 November 2026 that cites the superseded 2000 Act on application forms, newspaper notices, site notices or uses outdated statutory templates will be deemed invalid and returned.
Design teams and planning consultants finalising applications must verify whether their lodgement date falls before or after the midnight deadline and ensure the matching statutory templates are used.
However, applicants are advised not to rush to beat the Wednesday midnight deadline with an incomplete application. If the application has not been properly finalised, wait and lodge it under the new 2024 Act.
Key commercial and legal changes coming into effect
1. Reversal of ‘deemed compliance’ on condition submissions (Section 87)
This is the change that has the potential to catch the most projects off guard. Under the 2000 Act, if a planning authority failed to respond to a compliance submission within eight weeks, agreement was deemed granted by default. The 2024 Act reverses this rule entirely: where a planning authority fails to issue a decision within the statutory timeframe, the compliance submission is now deemed refused, triggering a right to refer the matter to An Coimisiún Pleanála for determination. Developers and funders must build additional lead-in time into pre-commencement construction programmes to avoid site delays.
Standard Irish building contracts, including the RIAI and Public Works suites were drafted for the old 2000 Act and do not clearly spell out who absorbs the cost of these new statutory delays. Until contracts catch up, developers and builders face messy disputes over extensions of time and standing costs, making robust paper trails and early council engagement essential from day one.
2. Overhaul of extensions of duration and alterations (Sections 140–147)
Under the 2000 Act, a developer seeking to extend a planning permission's lifespan had to demonstrate that ‘substantial works’ had been carried out (Section 42), while amendments to an existing permission were dealt with separately under Section 146A. Both procedures are now replaced by a single unified framework under Sections 140–147 of the 2024 Act.
Under the new framework, the threshold for extensions is lower, the developer need only show that development has ‘commenced’ rather than that substantial works are complete, but a new materiality test applies to both extensions and alterations. Where the authority determines that the request is ‘material,’ it triggers a process similar to a new planning application involving public participation, environmental screening, reassessment against the current Development Plan, and third-party appeal rights.
Transitional grace period: For holders of existing 2000 Act permissions, the old extension-of-duration rules under Section 42 continue to apply until 16 October 2027. Developers with legacy permissions approaching expiry should consider whether to bring an extension application forward before that date, to avoid having to satisfy the stricter 2024 Act regime.
3. Suspension of permission lifespan during judicial review (Section 180)
Under Section 180 (as reinforced by the Planning and Development (Amendment) Act 2026), the relevant planning permission duration is suspended (upon written notice being given to the planning authority by the developer) from the date Part 9 judicial review proceedings are initiated until those proceedings are finally determined. This prevents permissions from timing out while tied up in litigation. Section 180 (9) clarifies that such suspension does not apply to all permission types: it has no application to retention permissions, retrospective consents, extensions of duration under Chapter 5, or outline permissions within the meaning of section 96.
4. Mandatory statutory timelines for An Coimisiún Pleanála (Section 361)
Under the 2000 Act, An Bord Pleanála (the planning appeals board) operated under an 18-week decision target that carried no legal sanction when missed. Prolonged delays became routine, leaving developers and applicants with little recourse. An Coimisiún Pleanála replaces that body under the 2024 Act and operates on an entirely different basis. Its decision timelines are now mandatory by statute rather than aspirational targets, ranging from 18 weeks for straightforward appeals to 48 weeks for cases requiring full environmental assessment. Where the associated deadlines are breached, financial penalty mechanisms apply. This represents a significant structural shift towards a system of genuine accountability for delay.
5. Tighter rules on material contraventions and outline permissions
- Material contraventions (Sections 99, 113, 124, 148): Planning authorities face stricter statutory tests before granting permission in material contravention of a City or County Development Plan.
- Outline permissions (Section 96): Outline planning permission is now capped at residential developments of four units or fewer, eliminating outline applications for larger residential schemes.
6. Amendment of permission by planning authority
Section 277 of the 2024 Act introduces, for the first time, a statutory power enabling a planning authority to amend a planning permission after it has been granted. The new provision allows the chief executive or deputy chief executive of the planning authority to authorise a member of staff to amend a permission for the purposes of correcting a clerical error, facilitating something reasonably contemplated by the terms of the permission but not expressly provided for, clarifying the terms of the permission, or facilitating its implementation or operation.
Importantly, this power is strictly a correction and clarification mechanism and may not be used to effect a material alteration to the permitted development. The power extends to permissions granted under the 2000 Act but does not apply to outline permissions. For developers and their professional teams, Section 277 offers a welcome streamlined route to resolving minor drafting issues in granted permissions without the cost and delay of a new planning application.
What to do now
- Review live transaction documents: Check contracts for sale, development agreements, facility agreements, and conditional commercial leases where obligations or conditions precedent reference specific sections of the 2000 Act (such as Section 5 declarations or Section 34 permissions) to ensure contractual definitions capture the 2024 Act equivalents.
- Audit imminent lodgements: Confirm with your architect or planning consultant whether live applications will be lodged and validated before midnight on 25 November, or whether application forms, site notices, and newspaper notices must be re-drafted for the new regime.
- Review existing permission expiry dates: Identify any legacy 2000 Act permissions approaching expiry and assess whether an extension-of-duration application should be brought forward ahead of the 16 October 2027 transitional cut-off.
- Build in compliance lead times: Update construction schedules and drawdown conditions to reflect the new 'deemed refusal' default on planning condition compliance submissions.
- Review your building contracts: Check how planning risk and delay risks are allocated and agree clear amendments where the position is unclear under the new framework.
Our real estate team, advises developers, funders, and investors across the full project lifecycle from site acquisition and planning through to delivery and disposal. Our construction and engineering practice works closely alongside, advising on contract negotiation, risk allocation, and dispute avoidance and resolution. To discuss how the Planning and Development Act 2024 affects your projects, transactions, or contracts, please get in touch.
Disclaimer: The content of this article is intended to provide a general guide to the subject matter and does not constitute legal advice. Specialist planning advice should be sought for any specific planning law related issues.