PFI reset: NISTA guidance on reviewing and resetting distressed projects
NISTA’s PFI reset guidance explains how public authorities can assess whether a Private Finance Initiative (PFI) project needs a reset. Its Project Stocktake tool helps contracting authorities, project companies and service providers identify issues and agree next steps. We examine what the guidance means in practice, when a reset may be appropriate and the challenges of delivering one reflecting on our experience from previous and current projects.
NISTA has released new guidance on PFI resets aimed at PFI Contract SROs and Contract Managers which builds on the concept of resets set out in the White Fraiser report.
A summary of the guidance is available here: PFI Reset: An Introduction | GOV.UK.
The detailed guidance is available on the PFI Centre of Excellence Website here: PFI Centre of Excellence | GOV.UK.
What does the guidance cover?
The guidance (i) introduces the concept of a project reset, (ii) provides a ‘Project Stocktake’ tool as a means assessing whether a reset is required, and (iii) provides guidance relevant to the application of reset for public sector SROs and PFI contract management teams. The guidance is detailed and expansive and vital reading for those involved in managing and advising on PFI contracts, both on the public and private sector side.
Reset not required on every project
NISTA supports the concept of resetting distressed PFI projects, but stresses that each project requires a specific approach rather than a one-size-fits-all solution. NISTA notes that: “Each project is unique, with a different scope, relationships and subcontracting arrangements, and the reset process should reflect these differences. Importantly, not all projects require a reset.” NISTA continues to note that: “A reset should be considered where there are signs of material underperformance, strained relationships, governance challenges or concerns about asset condition. These issues may not always be visible without a structured review of your project.”
We are very happy to see NISTA stressing the fact that its advice is not intended to be used as a ‘cookie-cutter’. In our experience, client goals, the relationships they have with their contractual counterparties, the reasons for project distress, contractual terms and negotiation levers very significantly from project to project, even where contracting parties can be common across projects. For those reasons, we always advise clients to take a bespoke approach.
Successful PFI Projects have investment in resourcing
NISTA stresses: “Achieving the best outcomes from PFI contracts requires proactive management, collaboration and mutual accountability”. However, as NISTA notes, proactive management and accountability: “requires investment in resources, perseverance, and a genuine commitment to working together”.
NISTA further notes in the guidance that project resets cannot be dealt with as part of day to day activities and needs to be project managed separately. We endorse this approach. In our experience, active project management and the time to deal with project distress is crucial to achieving successful outcomes and avoiding and (where they are unavoidable) managing disputes.
What projects require resets?
Resets are likely to be required where projects have systemic shortcomings in relation to:
- dysfunctional working;
- a lack of data and transparency;
- a lack of effective governance;
- end user dissatisfaction;
- asset condition issues relating to construction defects or poor maintenance; and
- consistent issues around contractual interpretation impacting performance management.
Whether or not reset is required, and the scope of the reset should be determined by completing a ‘Project Stocktake’ process (mentioned below) which is introduced by the guidance as a means of helping assess how the project is operating and whether reset is relevant.
What does NISTA think resets look like?
NISTA gives examples of the approaches it has seen to implementing reset in practice which includes:
- refreshing existing operating procedures and mechanisms including liaison committee meetings;
- adeep interrogation of statutory maintenance compliance;
- resetting relationships;
- a resolution of contractual disputes via dispute resolution procedures; and
- root and branch reviews of asset conditions and operational performance.
Why should you review your project?
- Reviews test whether working relationships, behaviours and performance genuinely meet requirements. Undermanagement and inadequate oversight are recognised PFI problems, and public services and money are at stake.
- Failure to review and manage PFI disputes effectively risks service disruption, health and safety or statutory-compliance failures, poor value for money, post-expiry expenditure on maintenance that should already have been delivered (which is unlikely to be recovered from Project Co), and entrenched conflict leading to costly disputes.
What is the Project Stocktake?
The ‘Stocktake’ tool is a questionnaire format which NISTA recommends is carried out jointly with Project Co and the operational service provider. It recommends that each party completes the questionnaire separately and then meets to discuss the results and agree on next steps. The intention of the tool is not to generate an overall rating for each project, but to highlight required areas of focus to allow parties to compare and contrast results and focus on material issues.
The Project Reset Project Stocktake questionnaire is available here.
NISTA has made clear that the stocktake has been designed to reflect those themes which in NISTA’s experience are most important for well operating projects, being the following four themes:
- Governance;
- Resourcing;
- Contract Management; and
- Performance.
How should the results of the Project Stocktake to be used?
NISTA recommends discussing the results of the Stocktake with PFI SPVs and operational subcontractors with less material issues being resolved through existing contract management. Significant concerns may justify a reset using NISTA’s ‘Delivering PFI Reset’ guidance which you can access at the PFI Centre of Excellence webpage using the link provided above.
The key themes and questions asked by the Stocktake echo our own experience as to the key issues a contracting party needs to know to properly assess how its project is faring. Whilst it is not intended to be a detailed diagnostic tool and is instead designed to give a relatively quick assessment of the project. However, the facts remains that to do the stocktake properly will require significant preparation and discourse between contracting authorities, SPVs and operational subcontractors which underlines the comments raised above about adequate resourcing. It remains to be seen whether parties devote the time required to complete this Stocktake process with enough forethought and detail so as it fulfil its purpose.
Key issues in delivering a reset
As NISTA notes, resetting a project is about agreeing and delivering change. NISTA notes that this can be challenging for a number of reasons including:
- Building consensus on the required change can be complex and time consuming; and
- A lack of trust and transparency can hamper joint working.
In our experience another key challenge for significant reset or performance change is the financial impact. On projects with a record of underperformance and significant historic unitary charge deductions, Project SPVs may have little financial reserves, or buffer within its monthly cashflow to make any significant performance changes. Overcoming this challenge requires realistic and pragmatic outcome expectations from all parties.
What does the PFI supply chain think about resets?
The Associate of Infrastructure Investors in PPPs (AIIP), which is the trade body for UK PPP / PFI investors worked with NISTA to develop the reset guidance, drawing on the practical experience of its members. The private sector perspective set out in the guidance can be summarised as follows:
- Leadership and partnership: Contracting authorities, PFI company directors and service providers need strong leadership and a shared commitment to achieving assured performance together, based on shared values.
- Governance and escalation: Engagement should run from operational teams to SROs, with timely escalation to resolve issues and avoid surprises, barriers and undue delays.
- Communication: Parties should explain their positions carefully to prevent misunderstandings and avoid disputes that undermine relationships without improving operational outcomes.
- Continuous improvement: Both parties should be willing to review assets, services and contract management and administration, strengthening systems and processes to sustain high performance rather than making sudden, counterproductive changes.
- Resourcing: Reset activity may require additional resources, particularly technical expertise.
- Advisers’ accountability boundaries: Advisers may support either or both parties, but must not assume SROs’ or SPV directors’ roles, responsibilities or accountabilities, or unilaterally determine the course of the reset.
We hope the involvement of AIIP in the preparation of the guidance in conjunction with NISTA will assist in aligning expectations from both parties to a PFI contract as to what is required for project success, and what is realistic as to what can be achieved within the existing cashflows of the project or where a more major restructure such as equity cash injections or service variation is required.