planning and environmental law update


When is substantial completion anyway?


The Ardagh Glass case has more twists in it than a game of snakes and ladders and the game hasn’t even finished yet! In 2000, Quinn Glass approached Ellesmere Port and Neston Borough Council and Chester City Council to promote a major glass manufacturing facility. Approval was finally given in 2003, but then amendments were sought in 2004. The Councils took the view that these were minor amendments to the original planning permission but this decision was subject to a High Court challenge by Ardagh Glass (a competitor) and the decisions were quashed. Further applications were submitted in 2004 for the amended development which were subsequently called in by the Secretary of State. These were refused for a variety of reasons but the Secretary of State did indicate that the objections to the development may be overcome by a new application.

In April of last year a further High Court challenge was made by Ardagh Glass seeking an order to make both Councils issue an enforcement notice against the unauthorised facility and to prevent the Councils from determining the planning applications for the retrospective consent of the facility.

The case concerned two issues. The first being that enforcement action could not be taken after a period of four years from substantial completion and there were alternative views taken on the date from when the immunity started to run. Secondly, the claimant contended that it was impossible for the local planning authority to grant planning permission for Environmental Impact Assessment (EIA) development after the works had taken place – the provisions within the UK system for retrospective granting of planning permission was not consistent with the EIA Directive objectives.

In respect of the first issue, consideration was given to the case of Sage v Secretary of State [2003] UKHL 22 and what is meant by substantial completion. The key to this question is determining what the operations in question are. In the Sage case, the development was a single dwelling house and it was sensible for Lord Hobhouse to take a holistic view of development in that instance. The court rejected the defendant argument that the substantial completion will refer to those operations which are envisaged by the parties at the outset. Rather, the court preferred the view that where there is a complex development, it was entirely possible for the development to be made up of a number of operations and for immunity to occur on each distinct part. Which separate operations form each element of the development will be a matter of fact and degree in the circumstances of each case. However, what is clear is that for large developments, substantial completion will not necessarily be when the entire development is complete, rather individual elements will be capable of substantial completion at different times.

In the second issue, it was argued by the claimant that the EC directive on EIA required that, before consent is given for projects likely to have a significant effect on the environment, they are made subject to an EIA and that environmental assessment must occur before development commences. Therefore, the ability to grant retrospective planning consent for EIA development was inconsistent with EU law. This view was not shared by the court who were of the view that as long as a decision to grant development consent is preceded by a full and proper EIA and a full and genuine opportunity for the public to understand the proposals, express their views and have them taken into account, then this would not be contrary to Article 2(1) of the Directive. Where it is clear that the developer has obtained an advantage, such as less rigorous requirements from the EIA, then this will plainly be contrary to the Directive and retrospective development consent should not be granted. Therefore the judge refused to grant a declaratory order that planning permission could not be granted for the development retrospectively.

Subsequently, the local planning authority has resolved to grant planning permission subject to call in, which we understand the Secretary of State has decided not to do. However, both parties appealed the High Court decision and this will be heard in the Court of Appeal in the Spring. It is difficult to know with any certainty what the Court of Appeal will decide, however you shouldn’t bet against another twist in this long running saga.

talk to us


picture of Steve Coult
Steve Coult
0115 976 6152
Associate Planner
   

save to PDF
The content of this update is provided for the purposes of general interest and information. It contains only brief summaries of aspects of the subject matter and does not provide comprehensive statements of the law. It does not constitute legal advice and does not provide a substitute for it.

sign up
sign up
keep up-to-date with free legal bulletins, updates & training
more
return to planning update
return to planning update
click here to return to our planning and environmental update contents page
more