bulletin


The perils of proceeding on a ‘subject to contract’ basis


11 May 2010


The recent case of RTS Flexible Systems Ltd (RTS) v Molkeri Alois Muller Gmbh & Co (Muller) [2010] UKSC 14 has highlighted the risks involved in beginning projects without signing a contract and fully agreeing the terms of the project in advance.

What happened?

Muller, a well known supplier of dairy products, awarded RTS a contract worth £1.68 million for the supply of automated packing machines for packaging and product handling.

Muller and RTS agreed a ‘letter of intent’ in January 2005 setting out the contract price for the entire project and recording their intention to enter into the ‘MF/1’ model form of general conditions of contract (modified as appropriate) in due course. The letter also incorporated a standard clause as follows: “The Contract may be executed in any number of counterparts provided that it shall not become effective until each party has executed a counterpart and exchanged it with the other.”

The letter of intent expired in May 2005 but RTS continued to work on the contract and both parties continued to negotiate the terms of the contract.

RTS ran into difficulties with delivery of the original project timetable, and, although the equipment was subsequently delivered to Muller, RTS did not carry out the site acceptance testing provided for in the original tender document and the draft contract. Muller subsequently alleged that the product had defects and only paid part of the price. RTS brought a claim against Muller for the outstanding balance of the contract price. It also claimed damages.

What did the courts find?

RTS basically argued that there was no contract. If there was a contract, said RTS, then it included a statement that the agreement was subject to contract.

What had happened at first instance?

The Court of Appeal ruled that no contract had come into existence after the letter of intent had expired. Muller appealed this decision and the parties repeated their arguments to the Supreme Court.

The Supreme Court overturned the Court of Appeal decision, ruling that it was unrealistic to suppose that the parties did not intend to create legal relations, for the following reasons:

  • Both parties agreed the contract price and this was binding on both of them
  • If there was no contract, RTS would have effectively been agreeing to carry out works with no terms agreed at any point
  • A variation to the contract was agreed in August 2005 with no reference to the fact the variation was subject to contract
  • On the basis that a contract did exist, it was unrealistic not to treat the draft contract as a whole and as such this included the ‘subject to contract’ provision.

The Supreme Court therefore found that the parties had reached a binding agreement and by their conduct they had waived the ‘subject to contract’ statement.

What are the implications?

Even though this decision relates to the activities of two private sector organisations, it is nevertheless an important one for commissioners of public services because it means that where work is carried out prior to a contract being agreed, the protection offered by a ‘subject to contract’ provision may not actually be there.

As holders of the ‘public purse’, any failure to deliver services or facilities to the public has the potential to cause public embarrassment and/or increased scrutiny of the organisation dealings and arrangements.

Whilst commissioning schedules may mean that contractors are still required to begin work before the full and final contract has been settled and signed, public sector organisations must ensure they can demonstrate that they have taken active steps to reduce the risks as much as possible.

Before commencing work, commissioners should ensure that the key contractual terms are sufficiently and clearly documented in heads of terms, and that the final terms are agreed in a written contract as soon as possible thereafter.

If it is agreed that the heads of terms will expire on a particular date, it will be necessary for the parties to address the situation where work has begun but no formal contact has yet been signed.

The far better option, in any event, is to refrain from beginning any economic activity until a formal contract is in place – and to plan workstreams accordingly in order to achieve this.

talk to us


picture of Christopher Brennan
Christopher Brennan
0121 237 3964
Associate
picture of Emily Birkett
Emily Birkett
0121 237 3934
Solicitor
 


save to PDF


The content of this bulletin is provided for the purposes of general interest and information. It contains only brief summaries of aspects of the subject matter and does not provide comprehensive statements of the law. It does not constitute legal advice and does not provide a substitute for it.

sign up
sign up
keep up-to-date with free legal bulletins, updates & training
more
return to resources
return to resources
click here to return to our resources section
more