|
Adjudication and Construction Operations in Relation to
Plant
The Housing Grants, Construction and Regeneration Act 1996 ("the
Act") excludes the installation of plant in relation to a site
where the primary activity is water treatment from the definition
of a "construction operation" under the Act. As a result statutory
adjudication does not apply.
In the case of Comsite Projects Limited –v- Andritz AG, Andritz
sub-contracted to install plant on a site carrying out water
treatment works, and also to install services in the building of
the plant. Andritz in turn sub-contracted the wiring to the plant
and the installation of lighting and alarm systems in the plant
building to the Claimant, Comsite.
Disputes arise between Comsite and Andritz. Comsite wanted to
refer its claim to adjudication. Andritz argued that it could not
do, because Comsite's sub-contract was not a "construction
operation" within the meaning of the Act. Comsite went to court for
a declaration, amongst other things, that its contract was a
construction contract for the purposes of the Act. A further
complication was found that Comsite's contract contained a clause
conferring jurisdiction in relation to the settlement of disputes
arising from the interpretation or execution of the contract on the
Austrian, rather than English courts. Perhaps not surprisingly,
Andritz argued also that the English courts could not deal with the
matter because of that jurisdiction clause.
The court held that the jurisdiction clause concerning the
Austrian courts did not apply to adjudication proceedings under the
Act. This was because such proceedings did not concern the
interpretation or execution of the contract.
Further, the court held that because none of the services
supplied by Comsite was connected to the plant, or used to enable
the plant to operate, that Comsite were not installing "plant" and,
therefore, their works under the contract were construction
operations for the purposes of the Act and they could, therefore,
adjudicate.
Despite the ruling in the court, the English courts will only
have a temporary right to be involved in this matter, in that they
can only deal with any enforcement of the adjudication decision.
Andritz has the right to refer the matter back to the courts for
final determination, in which event the jurisdiction of the courts
would apply and the matter would have to be dealt with by the
Austrian courts. However, until that time, the decision of the
English courts in relation to the adjudication issues, must be
complied with. The significance of this case is that parties to a
contract should not assume that simply because there is a
jurisdiction clause to a foreign court contained within that
contract, that they have no right to adjudicate in England under
the Act.