healthcare update - issue 14


The Local Democracy, Economic Development and Construction Act 2009 - putting you on notice!


The Local Democracy, Economic Development and Construction Act 2009 became an Act on 12 November 2009 and although there is currently no commencement date for the provisions of part 8 which relate to construction contracts they may well come into force by the end of the year.

The Act applies to construction contracts which are contracts for the carrying out of construction operations and makes substantive changes to the current law, the Housing Grants, Construction and Regeneration Act 1996, rather than replacing it wholesale.

Summary of the key changes

  • It now applies to unwritten as well as written contracts
  • Adjudicators are now able to correct clerical and typographical mistakes in their judgments
  • “Tolent” clauses which state that the party bringing the adjudication would in any event bear both parties’ costs as well as the adjudicator’s have been outlawed and (broadly) parties may now agree that the adjudicator can decide who pays his fees and costs
  • Payment clauses which make payment conditional on the performance of obligations under another contract are ineffective – so pay when certified clauses and similar are ineffective. There is an exception which allows two parties to a construction contract to make payment under their contract conditional on a third party performing construction operations whether as a sub-contract or otherwise
  • A party may now suspend performance of just some rather than all of their obligations in the event of non-payment, a refinement to the current law
  • If a party suspends their performance because of non payment they may also recover the costs of suspension and re-mobilising as well as obtaining extra time to recommence following payment
  • A contract may state that if the payee becomes insolvent then payment may be withheld, and if the payee becomes insolvent when it is too late to serve the Notice of Intention to Pay Less then payment may still be withheld despite this – otherwise he has to serve the notice
  • The Secretary of State has the discretion to provide that some or all of the Act will not apply to certain types of contract however, it should be noted that it is not yet clear which ones, if any, these will be

Payment notices

A significant change under the new Act is that to the contractual payment mechanisms and the notices to be served. If the new regime is not understood, and the relevant notices not served then the paying party will be caught out.

The Act requires that under the construction contract no later than 5 days after the payment due date either the payer or a third party (most likely to be the contract administrator) is to give a ‘Payment Notice’ which specifies the sum which they consider is payable as at the payment due date and explains the basis on which it is calculated. The notice still has to be given even if the amount in question is zero. The parties may also agree, unlikely, that the payee may give this payment notice.

If the party who is supposed to give the notice defaults in providing it then the other party may give it. The sum which is then payable under the contract is the sum stated in the Payment Notice.

What is important is that if the payer/third party do not serve a compliant notice the payee’s application for payment can stand as the notice and the notified sum is the sum which is due to be paid under the contract.

The difference from the current regime is that while presently a similar notice should be served under s. 110 of the existing act there isn’t an effective sanction if it is not served. Also, unlike the new Act the current act does not state that the sum payable under the contract is the amount stated in the payment notice or that the payee can serve a notice if the payer fails to do so. The present default position tends to be that the sum payable is the sum properly due under the appointment or the building contract – such as the JCT. This will change when the Act comes into force.

If the payer does find himself in default of the Act’s payment notice requirements and believes that a lesser amount is payable then in order for him legitimately to pay less he has to serve a ‘Notice of Intention To Pay Less’. As with the Payment Notice this has to specify both the amount which the payer considers to be due on the date the notice is served and the basis on which that sum is calculated. This has to be served no later than the prescribed period (in default seven days) before the final date for payment.

The difference between the Notice of Intention to Pay Less and the current withholding notice is that the latter is only required to specify the amount to be withheld and the ground(s) for withholding – not the amount to be paid and the basis on which it is calculated.

Conclusion

The new era of ‘austerity’ heralded in the emergency budget launched on the 22 June means that there will be pressure to significantly postpone new construction projects. However, with the implementation of the new Premises Assurance Model pre-existing building commitments and those building works necessary to bring premises up to ‘standard’ are likely to be sanctioned. In an era when every penny will count, and operations become subject to greater audit scrutiny whether under PAM or otherwise, NHS Trusts need to be on the ball when it comes to their contractual arrangements, and to be aware of the changes which the Act will make when it comes into force to avoid being caught out.

talk to us


picture of Shaun Tame
Shaun Tame
0121 237 4552
Consultant
   

save to PDF

The content of this update is provided for the purposes of general interest and information. It contains only brief summaries of aspects of the subject matter and does not provide comprehensive statements of the law. It does not constitute legal advice and does not provide a substitute for it.

sign up
sign up
keep up-to-date with free legal bulletins, updates & training
more
return to healthcare update
return to healthcare update
click here to return to our healthcare update contents page
more