bulletin


A waste of a challenge


3 June 2010


The High Court has applied the recent European Court of Justice ruling in Uniplex (UK) Limited v NHS Business Services Authority (Case C-406/08) by dismissing a challenge to a public procurement procedure after the defendant successfully argued that the action had been brought outside the three month time limit from when it knew (or ought to have known) that there had been an apparent infringement of the EU procurement rules.

The facts of the case

In the case, Sita UK Ltd v Greater Manchester Waste Disposal Authority, the contracting authority (GMWD) began a tender procedure for a PFI project to provide waste disposal facilities for Greater Manchester in 2006. Sita led a consortium which submitted a bid, which was one of two bids to make it to the final round. On 27 January 2007, GMWD announced that it had selected the other final bidder, Viridor Laing (Greater Manchester) Limited, as the preferred bidder and on 18 April 2008 announced that it intended to enter into a contract with Viridor.

The contract was entered into on 8 April 2009 and Sita subsequently went to court on 27 August 2009, claiming that Viridor’s bid could not be said to be the most economically advantageous bid because it had substantially changed in nature between 2007 and 2009.

GMWD made an application for the claim to be struck out on the basis that the statutory limitation period of three months began to run on 8 April 2009 and that Sita was therefore out of time.

Application of the Uniplex decision

The High Court considered three questions which it considered needed clarifying before it could apply the ruling in Uniplex. These were as follows:

i. Grounds for bringing proceedings

The Uniplex judgment did not consider what grounds would trigger the start of the limitation period. Sita tried to establish that grounds included the infringement itself and some potential damage, whilst GMWD argued that only knowledge of the infringement itself was required.

The High Court agreed that the relevant grounds existed just in the infringement. Its reasoning was that the date of the infringement was relatively easy to identify, whereas the date on which related losses might be identified was not.

ii. Level of knowledge required to bring proceedings

Sita argued that it did not have sufficient knowledge on which to base its claim until July 2009, because it was awaiting facts demonstrating the breach as opposed to facts which simply indicated an infringement.

GMWD cited the Advocate General’s opinion in Uniplex, which stated that once a bidder had received the “essential reasons” for being unsuccessful it could generally be assumed that they had sufficient knowledge of an infringement to bring a claim.

The High Court rejected Sita’s argument, ruling that the deciding factor was the point when the aggrieved bidder first knew (or ought to have known) that it had a cause of action. It decided that Sita had had enough information by April 2009 to begin proceedings.

iii. Extension of time

The High Court accepted that GMWD had agreed to some extensions of time whilst in the process of providing further information requested. It therefore considered whether it should exercise its discretion to extend the time limit.

In making that decision, the High Court considered the public interest in scrutiny of GMWD’s conduct; an alleged lack of openness on the part of GMWD; whether any prejudice would be caused to GMWD if an extension was granted; and the requirement that Sita act ‘promptly’ in bringing proceedings.

The High Court noted that GMWD had not acted transparently in disclosing information to Sita, but ultimately decided that the first three factors did not carry sufficient weight to justify an extension of time. It also ruled that the delay of a month and a half between Sita receiving the further information from GMWD and filing a claim did not satisfy the promptness requirement. And so it concluded that an extension of time should not be allowed.

What does this mean for contracting authorities?

This case is the first one to apply the Uniplex judgment in the United Kingdom and should be welcomed by contracting authorities because it provides important clarification.

In practical terms, the judgment reduces the risk posed after the ruling in Uniplex whereby aggrieved bidders might make repeated requests for clarification of the reasons for not being awarded a contract. This is because it is clear from this case that knowledge of the existence of an infringement, as opposed to knowledge of the infringement and that any particular damage or loss has been caused, is sufficient to trigger the start of the limitation period.

The case also makes clear that whilst, following Uniplex, contracting authorities are unable to argue that claims should be struck out because they have not been brought sufficiently promptly, the overall objective remains one of rapidity. Courts are therefore still free to consider whether the claim was progressed promptly when considering whether or not to exercise their discretion and grant aggrieved bidders extensions of time for bringing proceedings.

talk to us


picture of Peter Ware
Peter Ware
0115 976 6242
Partner
picture of Emily Birkett
Emily Birkett
0121 237 3934
Solicitor
 

save to PDF

The content of this bulletin is provided for the purposes of general interest and information. It contains only brief summaries of aspects of the subject matter and does not provide comprehensive statements of the law. It does not constitute legal advice and does not provide a substitute for it.

sign up
sign up
keep up-to-date with free legal bulletins, updates & training
more
return to resources
return to resources
click here to return to our resources section
more