article


Successful procurement


29 September 2009


It has been an interesting few months for anyone involved in public procurement.   There has been a flurry of cases brought before the UK courts and the European Court of Justice (ECJ) which may affect the Fire & Rescue Service over the coming months.

Variation to procured contracts

In Pressetext Nachrichtenagentur GmbH v The Republik Österreich (Bund) the ECJ considered to what extent amendments to an existing procured contract constituted the award of a new contract under the public procurement rules.  The claim brought by Pressetext principally revolved around two things: at what stage do amendments made to a procured contract actually mean that a new contract is being awarded and whether it was ever permissible to assign a public contract to a new provider.


In its judgment, the ECJ stated that where amendments are made to the provisions of a public contract which are materially different from the provisions of the original contract, the parties are effectively awarding a new contract and accordingly, the relevant procurement rules would need to be followed before such award.

The Court suggested that the following factors could influence whether an amendment would be material:

  • conditions which, had they been part of the initial award procedure, would have allowed other tenderers to tender or the acceptance of an alternative tender;
  • extending the scope of the contract considerably to include services not initially covered; or
  • changing the economic balance of the contract to favour the contractor in a manner not provided for in the terms of the initial contract.

The Court specifically assessed whether amendments to pricing mechanisms would be material.  It stated that changing a pricing mechanism could potentially conflict with the principles of transparency and equal treatment although this was not found to be in the circumstance of the case.

The Court stated that ordinarily assignment could amount to a substantial amendment and thus a new award. However, as the transferee was a wholly owned subsidiary of the original service provider, there was no change in overall performance of the contract and that the original contracting party remained jointly and severally liable for performance the court concluded that there was no new award.

This case has offered guidance on the extent to which variations and transfer of contracts procured pursuant to the EU rules can be made.  However, much will depend on the facts of each individual case and careful thought will need to given to any actions taken in relation to procured contracts.

Disclosing evaluation Criteria

The Court of Appeal have recently upheld an interim injunction sought by Lettings International Limited (Lettings) against the London Borough of Newham which prevented it from completing a framework agreement, following, what Lettings had argued, was a flawed procurement exercise. 

Newham had issued a notice for 2 framework contracts.  The Invitation to Tender indicated that tenders would be evaluated by reference to 3 criteria, compliance with specification, price, and premises.  At completion of the evaluation Lettings challenged the award alleging that Newham’s assessment of compliance with the specification was actually carried out by reference to 5 sub-criteria which had not been disclosed in any of the contract documents or the contract notice. 

Two points of interest come from this case. First, it is one of the few UK cases to uphold an injunction preventing award and secondly, it gave further guidance on Regulation 30 of the Public Contracts Regulations 2006 which requires a contracting authority to state clearly, evaluation criteria weightings.  

In granting the injunction, the Court stated that it was not necessary to show that a tender would have been successful but for the alleged breaches. All that was needed was to show that there was a breach of the requirement for transparency and fairness which amounted to a loss of opportunity to take part in a properly conducted tender process.

Interestingly, in granting the injunction the Court considered that Newham was unlikely to need to immediately award contracts under the framework arrangements and that the inability to utilise them was not going to prejudice its ability to discharge its functions.

Considering the use of the sub-criteria the court stated that bidders must be aware of the relative importance of all evaluation criteria to allow proper preparation of bids.  The court felt that the sub-criteria were treated as additional formal criteria which should have been in the contract documents.  The Court also felt that the way in which bids were scored had not been made clear meaning bidders didn’t know what they had to do to get full marks. 

Rounding Up

These two cases set out some important considerations for The Fire Service. It is important to ensure all contract documents are clear, all evaluation criteria is set out so that tenderers know what they are bidding against and the procured agreements are sufficiently flexible to provide what is needed throughout the term. Once in place the scope to change them in any material way may be limited.

save to PDF

related services & sectors
procurement  fire services 
return to press office
return to press office
click here to return to the press office
more