article


Procurement - playing it safe


1 April 2009


Every Fire Authority has a statutory duty to ensure that the procurement of supplies, works and services represents the most cost-effective solution and that best value for money has been achieved. So in these troubled times how does the smart Fire Authority set about protecting itself when procuring works and services? Whilst there are no guarantees Shaun Tame, Construction Partner at Browne Jacobson LLP, outlines ten steps which can help to reduce the risk of the credit crunch derailing a project.

Conduct financial due diligence

This is crucial and should include due diligence exercises on sub-contractors as well. Make the supply of necessary financial information from tenderers a prerequisite. Take up financial references, speak to the referees and satisfy yourself that the contractor is financially sound. Authorities are perfectly entitled to make the financial position of a company something which you will take into account when evaluating and scoring tenders – you just need to be quite clear that you are doing so. Consider making it a term of the tender that the contractor has to produce similar information in respect of the proposed supply chain.

Take up references

Make it a term of the Invitation to Tender and the scoring mechanism that satisfactory references are obtained from recent clients.

Allow contractors and consultants to make a profit

Organisations need to make a profit to survive and clients aren’t doing themselves any favours by driving suppliers into the ground. The risk of going with the cheapest price is that the contractor doesn’t resource the project properly, quality suffers, extras are claimed at every opportunity and a claims mentality develops.

Worst of all, the cheapest contractor goes bust or fails to pay its suppliers and they either go bust or refuse to do the work. Either way, the negative consequences are likely to far outweigh the monetary benefits achieved by the saving in price.

Obtain parent company guarantees and bonds

A parent company guarantee won’t cover every eventuality but at least it protects the client against a situation where a subsidiary folds. A bond will cost money to procure – and it is usually only for 10% of the contract sum, but if it does have to be called on then depending on timing and the nature of the default it could very well provide a useful level of recompense. Make sure that the bond allows recovery in the event of insolvency and that it doesn’t expire until the issue of the certificate of making good defects.

Open a project bank account

While this may not be appropriate in all cases it is a possibility and one envisaged by the latest edition of one form of partnering contract – PPC 2000. The bank account run jointly by the employer and the main contractor will ensure that payments to the supply chain are being made when they should be made and that the contractor is neither sitting on monies when he should be paying thereby causing problems down the line – and so that if he goes bust he doesn’t take monies which should have been paid to the supply chain with him.

Sign contracts and obtain bonds and guarantees

Ensure that the contracts are actually signed and that bonds and guarantees are obtained. If they are not and the contractor or supplier goes bust or fails to deliver then you will not have the benefits which these contracts can offer.

Be a responsible client

Don’t be a soft touch but pay what is properly due when it is due. Don’t cause pressure on those involved on the job by paying late. Another aspect to this is running the tender process by the book and on time.

Get involved and manage actively

That way you should get early warning if there are problems and be better placed to resolve them or act appropriately. Also ensure that there is an early warning mechanism in the contract. In practical terms this might be achieved by being around the site regularly, having frequent informal and formal meetings and speaking to people. Monitor progress, make sure that what should be done is being done – ask questions and get answers.

Set aside off site materials and obtain vesting certificates

If you are paying for off site materials or equipment then ensure that you obtain a vesting certificate from the manufacturer or original supplier and make sure that in your agreement with your contractor you are only obliged to pay for the goods once this is produced.

Insist on step-in clauses

Obtain sub-contractor collateral warranties which contain step-in clauses so as to enable you to step into sub-contracts and finish the works if the main contractor fails.

save to PDF

return to press office
return to press office
click here to return to press office
more