article



Counting your losses


5 March 2008


C A Blackwell (Contractors) Ltd v Gerling Allegemeine Verischerungs-AG

A court case has provided a useful reminder as to the issues faced by contractors when seeking to recover against an ‘all risks' insurance policy. One of the findings was that the eventual loss must be accidental, even if other events leading to that outcome were not. Michael Sadler and Nik Carle from Browne Jacobson's Financial and Professional Risks team examine the implications for contractors in arranging appropriate insurance cover.

“Blackwell - a civil engineering contractor - won the tender to carry out earthworks, installation of the foundations and temporary drainage for the M60 motorway. As part of its risk analysis it included an additional 16.5% of the sub-contract price towards unforeseen ground conditions and weather. Blackwell had taken out an insurance policy with Gerling for the years to 31 December 1998 and 1999.

“As part of the foundations to the motorway, Blackwell laid the 'formation level', which was achieved by spreading imported capping material supplied and selected by the main contractor, Balfour Beatty. The main contractor selected shale for this purpose, a material that is generally known in the construction industry to breakdown and turn to slurry when wet.

“The works started in 1998, but due to bad weather the spring earth-moving season in 1999 started late. As a result, bulk earthworks were still being completed late in 1999 and two instances of heavy rain, the first in early October and the second in early December caused £534,975 of damage. The temporary drainage that Blackwell had put in place had proved insufficient.

“Blackwell made a claim for this loss under its insurance policy but Gerling denied liability raising the following main arguments that had to be decided by the court:

Was the policy an 'all risks' policy?

Although the policy was entitled "Contractors all risks" the operative wording of the policy covered "…all Damage … of whatsoever nature" rather than 'all risks…'. Blackwell argued that this was not an all risks policy, but instead a policy insuring specified risks. This is important because depending on the outcome, the following issue arose,

Was the loss fortuitous?

If the court found that it was in fact an 'all-risks policy' then as a matter of law the loss has to be 'fortuitous' – i.e. accidental. Gerling claimed that rainfall was not fortuitous and that Blackwell had assessed this in its tender. Gerling claimed that the damage was therefore certain and was not covered under the policy. Obviously Blackwell was keen to avoid having to argue this point.

Was the loss caused by Blackwell's wilful misconduct?

 It is common ground that a contractor is not entitled to recover a loss under its all-risks policy which it has brought about by wilful misconduct. Gerling argued that by providing inadequate temporary drainage during the winter months, Blackwell was not entitled to an indemnity.

The Contractor lost its argument that its insurance policy was not an 'all risks' policy. Therefore ‘fortuity’ was required by the policy, but what does this mean in practice?

Judge Mackie, who ruled on the case, found that a combination of factors had contributed to the loss including: the quality of the capping material which was approved by others; the earthworks being undertaken out of season because the programme was behind schedule; heavy rainfall; and the temporary drainage systems used.

As a result he concluded that:

"There was and could be nothing inevitable about incidents caused by what, on the evidence of Gerling's own expert, is the coming together of different factors culminating in heavy (but not exceptional) falls of rain… It follows that the damage caused by the incidents was fortuitous."

The Court went on to conclude that Blackwell was not guilty of wilful misconduct for there was no evidence that Blackwell knew of a risk and had deliberately ran that risk without taking precautions.

Contractors may therefore wish to consider their all-risks policy coverage and the types of loss that might not be covered, i.e. are you assessing risk by the use of risk analysis and running that risk? Without other intervening factors, it might be open to insurers to argue that the loss was not fortuitous and therefore not covered under the all-risks policy. That might also be the outcome if contractors are found to have been reckless or grossly negligent in causing the loss.

Clearly, in the light of this case, contractors should now engage their insurers or solicitors to review the wording of their policies. This is not a complicated process, but they do need to think about specific risks that they are taking on and ensure that they have cover for specific activities.”

save to PDF

related services & sectors
professional indemnity  property dispute resolution 
return to press office
return to press office
click here to return to the press office
more