article


Clawing Back Costs


17 March 2009


Submitting a tender can be incredibly time consuming and expensive, particularly given complex procurement structures. Traditionally, the response from contractors and consultants who have lost money in an unsuccessful tender has been to lick their wounds and simply get on with it, preferring to spend their resources chasing new business than challenging the tender process itself. However, as the recession bites and the issue of liquidity becomes ever more important, such contractors and consultants may be more inclined than usual to seek repayment of their tendering costs and future loss of profit.  

But are those costs recoverable? Well, as would be expected, there are differences when dealing with the heavily regulated public sector as opposed to the private sector.

In the private sector the tendering process is not covered by public procurement regulations and traditionally the courts have had little sympathy for unsuccessful tenderers, taking the view that they should properly bear the consequences of a risk they have consciously taken. Except in exceptional circumstances (usually involving negligent misrepresentation or fraud), the courts are reluctant to regulate pre-contract negotiations or to help soften the blow of a disproportionately harsh bargain. That said, there have been other notable exceptions.

Damages may be recoverable by a disgruntled tenderer in certain circumstances. The key is to look at the tender process and, more particularly, what risk has been accepted by the tenderer. In the absence of a clear agreement that the work undertaken in the tender process is ‘subject to contract’, damages may be recoverable depending upon whether the work is of a kind usually provided free during a tender process; whether the contractor has accepted that such work would be unpaid; if the employer has gained any material benefit; and if the failure to award a contract involves any fault on the part of the employer. This will turn on the facts of each case.

In addition, where there is unfairness in the tender process itself, the courts have indicated that they may offer some relief for the affected tenderer. Such unfairness could feasibly occur where tenders have not been assessed according to the stated tender criteria, and if tenders are not evaluated in a uniform manner.

For example, in the Northern Ireland case of J&A Developments Limited v Edina Manufacturing Limited [2006], Edina invited J&A along with 5 other contractors to tender for works. The tender document provided for the tendering procedure to be carried out in accordance with the Code of Procedure for Single Stage Selective Tendering 1996. J&A submitted the lowest tender, but was not awarded the contract because Edina subsequently conducted a “dutch auction” – Edina invited the participating contractors to reduce their tenders through negotiation. Subsequently, the contract was awarded to the second lowest tenderer, in breach of the Code. The Court decided the wording of the tender documents gave rise to a contractual obligation limiting the manner in which Edina could conduct the tender process. Edina had breached that obligation. Consequently, J&A were entitled to recover their costs of preparing the tender. Further, because on the facts J&A would have almost certainly been awarded the tender had Edina followed the Code, J&A were entitled to recover an element of their anticipated loss of profit.

Additional protection for tenderers is found in the public sector. Procurement of public works over the current thresholdin England and Wales is regulated by the Public Contracts Regulations 2006

Under the Regulations a contracting authority owes a duty to tenderers to award contracts based on objective criteria, ensuring compliance with the principles of transparency, non discrimination and equal treatment in conditions of effective competition.  If an authority breaches that duty to the detriment of an unsuccessful tenderer, then that tenderer may have an action against the authority if they suffer, or risk suffering, loss or damage.. Damages are awarded based on that tenderer having lost the chance of successfully tendering, had the rules been followed, and later making a profit plus any abortive tender costs. 

Disgruntled tenderers need to bring proceedings promptly and in any event within 3 months from the date when the ground or grounds for bringing the proceedings first arose (unless the court can be persuaded that there is good reason for extending this time limit).

With the market conditions being what they are and the courts leaving the door ajar to tenderers who have not consciously forgone the right to payment or who have otherwise been treated unfairly in the tender process itself, this may well prove to be a growth area for claims in the foreseeable future both in the private and public sectors. Consequently, tender processes (and the consultants who run them) may find themselves subject to ever increasing scrutiny.

save to PDF

return to press office
return to press office
click here to return to the press office
more